EAC = AC + (BAC − EV) / (CPI × SPI)σpath = √(Σ σ²activity)NPV = Σ Ct / (1 + r)t

Quantitative methods for project management

Every calculation method inside ICB4 scope, with the formula, a worked example in numbers, and a diagram where the shape of the answer matters more than the arithmetic. Each method is mapped to the ICB4 competence element it serves.

75 methods · 14 groups · mapped to ICB4

How to use this. Each method has four parts: what it answers, the formula, a worked example with real numbers, and where relevant a diagram. Worked examples use invented but internally consistent figures — they exist to show the mechanics, not to represent any real project. The amber blocks flag the specific mistakes that cost marks.

Scope note: IPMA publishes no official list of quantitative methods. This document covers the calculation methods that fall inside the ICB4 competence elements, and maps each one to the element it serves. It is not a statement of what any specific certification body tests.

A  Time ICB4 4.5.4

A1 Critical path method

Primary 4.5.4 Time · KCI 4.5.4.4 Sequence project activities and create a schedule

How long the project takes, which activities cannot slip, and how much slack the rest have.

You build a network of activities with dependencies, push dates forward through it to get the earliest each activity can happen, then pull dates backward from the project finish to get the latest each can happen without delaying the end. The gap between them is float.

Forward pass EF = ES + Duration ES = max(EF of all predecessors) Backward pass LS = LF − Duration LF = min(LS of all successors) Total float TF = LS − ES = LF − EF Free float FF = min(ES of successors) − EF Critical path the chain of activities where TF = 0
033 A 003 347 B 307 325 C 527 7512 D 7012 538 E 9412 End12 Node key: ES | Dur | EF / name / LS | TF | LF red = critical path (TF = 0)
Activity-on-node network. A–B–D is critical at 12 days. C carries 2 days of total float, E carries 4.

Worked example

Five activities. A (3d) starts the project. B (4d) and C (2d) both follow A. D (5d) needs both B and C. E (3d) needs C only.

Forward pass A: ES 0, EF 0+3 = 3 B: ES 3, EF 3+4 = 7 C: ES 3, EF 3+2 = 5 D: ES = max(EF_B, EF_C) = max(7, 5) = 7, EF = 7+5 = 12 E: ES 5, EF 5+3 = 8 Project duration = max(12, 8) = 12 days Backward pass (project LF = 12) D: LF 12, LS 12−5 = 7 E: LF 12, LS 12−3 = 9 B: LF = LS_D = 7, LS = 7−4 = 3 C: LF = min(LS_D, LS_E) = min(7, 9) = 7, LS = 7−2 = 5 A: LF = min(LS_B, LS_C) = min(3, 5) = 3, LS = 3−3 = 0 Total float A 0 B 0 C 5−3 = 2 D 0 E 9−5 = 4 Free float of C min(ES_D, ES_E) − EF_C = min(7, 5) − 5 = 0 Critical path A → B → D = 3 + 4 + 5 = 12 days

C has two days of total float but zero free float: delaying C by even one day pushes E, because E starts the moment C finishes. Total float belongs to the path, free float belongs to the activity alone.

Exam trap. Take the minimum on the backward pass and the maximum on the forward pass. Reversing them is the single most common arithmetic error, and it silently produces a plausible-looking wrong critical path. Also: a network can have more than one critical path, and float can be negative if an imposed finish date is earlier than the calculated one.

A2 Precedence relationships and lags

Primary 4.5.4 Time · KCI 4.5.4.4 Sequence project activities and create a schedule

How two activities are actually tied together, and how much the tie shifts the dates.

Four relationship types exist. Each constrains a different pair of endpoints, so each changes the forward-pass formula. A lag adds waiting time to the constraint; a lead (negative lag) removes it.

FS Finish-to-Start ESsucc = EFpred + lag most common SS Start-to-Start ESsucc = ESpred + lag FF Finish-to-Finish EFsucc = EFpred + lag SF Start-to-Finish EFsucc = ESpred + lag rare, used in handovers
FS + 2d lag predecessor successor 2d SS + 1d lag predecessor successor FF + 0d lag predecessor successor SF predecessor successor old system runs until new one starts
The four dependency types. Shading marks the predecessor; the dashed line marks the constrained pair of endpoints.

Worked example

Data migration (10d) and reconciliation testing (6d), linked SS + 3d. Migration starts on day 0.

Migration: ES 0, EF 10 Testing (SS+3): ES = ES_migration + 3 = 3, EF = 3 + 6 = 9 Same pair as FS + 0: Testing (FS): ES = EF_migration = 10, EF = 16 → 7 days later

Choosing SS over FS shortened the pair by seven days at the cost of running the two activities concurrently, which is the definition of fast-tracking (A4).

Exam trap. An SS or FF link only constrains one end of the successor. The other end floats freely, so an FF-linked successor can be dragged earlier or later without violating the logic. When a question asks for a duration after adding an SS link, check whether the successor's own duration, not the link, is now driving the finish.

A3 PERT and probabilistic duration

Primary 4.5.4 Time · KCI 4.5.4.2 Determine the work effort and duration of activities Also 4.5.11 Risk and opportunity

How long an uncertain activity takes on average, and what the odds are of hitting a given date.

PERT replaces a single duration guess with three: optimistic, most likely, pessimistic. The weighted mean gives an expected duration; the range gives a standard deviation. Add variances along a path and you can attach a probability to any target date via the normal distribution.

Expected duration te = (O + 4M + P) / 6 beta-PERT Triangular mean te = (O + M + P) / 3 Std deviation σ = (P − O) / 6 Variance σ² = ((P − O) / 6)² Path std deviation σpath = √(σ²1 + σ²2 + … + σ²n) Z-score z = (target date − expected date) / σpath
12.0 d expected (P50) 14.0 d target, z = +2.0 σ = 1.0 d 97.7% chance of finishing on or before day 14 1013
Path duration as a distribution. The mean is the PERT sum; the spread comes from the summed variances.

Worked example

Critical path A–B–D from A1, now estimated in three points.

ActivityOMPteσσ²
A2343.000.3330.111
B2464.000.6670.444
D3575.000.6670.444
Path———12.001.000.999
t_e(B) = (2 + 4×4 + 6) / 6 = 24 / 6 = 4.0 days σ(B) = (6 − 2) / 6 = 0.667 → σ² = 0.444 σ_path = √(0.111 + 0.444 + 0.444) = √0.999 = 1.00 day P(finish ≤ 14 days): z = (14 − 12) / 1.00 = +2.00 → 97.7% P(finish ≤ 13 days): z = (13 − 12) / 1.00 = +1.00 → 84.1% P(finish ≤ 12 days): z = 0 → 50.0% Date giving 90% confidence: z = 1.282 → 12 + 1.282(1.00) = 13.3 days
Exam trap. Add variances, never standard deviations. √(0.111+0.444+0.444) = 1.00, but 0.333+0.667+0.667 = 1.667 — a 67% overstatement. Second trap: the single-point CPM duration equals the PERT mean only by coincidence; a right-skewed estimate (P far from M) pushes te above M. Memorise z = 1.282 for 90%, 1.645 for 95%, 2.326 for 99%.

A4 Schedule compression — crashing and fast-tracking

Primary 4.5.4 Time · KCI 4.5.4.5 Monitor progress against the schedule and make any necessary adjustments Also 4.5.7 Finance

The cheapest way to buy back schedule, and what it costs per day.

Crashing adds resources to shorten activities and always costs money. Fast-tracking overlaps activities that were sequential and costs rework risk instead. For crashing, you rank critical activities by cost slope and buy the cheapest days first.

Cost slope = (crash cost − normal cost) / (normal duration − crash duration) = cost per day saved Procedure 1. crash only activities on the critical path 2. take the lowest cost slope first 3. respect each activity's crash limit 4. after every step, recalculate — another path may go critical
indirect cost direct cost optimum project duration → shorter to the right total cost 14d13d 12d11d10d
Direct cost rises as you compress; indirect cost falls with duration. Total cost has a minimum, and it is rarely at either extreme.

Worked example

Critical path A–B–D, 12 days. Target: 10 days.

ActivityNormalNormal costCrashCrash costMax daysSlope
A3d30,0002d38,00018,000/d
B4d40,0002d52,00026,000/d
D5d50,0004d57,00017,000/d
Slope B = (52,000 − 40,000) / (4 − 2) = 12,000 / 2 = 6,000 per day ← cheapest Step 1: crash B by 1 day → path A-B-D = 11d, added cost 6,000 Step 2: crash B by 1 more → path A-B-D = 10d, added cost 6,000 (B now at crash limit) Re-check all paths at 10 days A-B-D = 3 + 2 + 5 = 10 critical A-C-D = 3 + 2 + 5 = 10 now also critical A-C-E = 3 + 2 + 3 = 8 Target met. Total crash premium = 12,000 for 2 days. To reach 9 days you can no longer crash B. The next day must come from an activity on both critical paths: A (8,000/d) or D (7,000/d) → crash D, 7,000.
Exam trap. Crashing a non-critical activity buys nothing and is a guaranteed mark lost. And once a second path goes critical, a single activity crash no longer shortens the project unless that activity sits on every critical path — otherwise you must crash one activity on each path, and the effective cost per day is the sum of their slopes.

A5 Milestone trend analysis

Primary 4.5.4 Time · KCI 4.5.4.5 Monitor progress against the schedule and make any necessary adjustments Also 4.5.10 Plan and control

Whether your milestone forecasts are drifting, and in which direction, across successive reports.

At each reporting date you re-forecast every milestone's finish date and plot it. Reporting dates run along one axis, forecast dates along the other. A horizontal line means a stable forecast. A rising line means the milestone keeps slipping. A falling line means it keeps being pulled earlier, which usually signals over-optimistic replanning rather than genuine recovery.

Reading the slope horizontal → forecast stable, plan is holding rising → slipping; slope of 1.0 means one day lost per day elapsed falling → forecast pulled in; check whether scope moved with it crossing the diagonal → milestone reached
reporting date = forecast date M2 design freeze — stable M3 go-live — slipping ~2 wks/report M1 UAT start — pulled in reporting date forecast milestone date JanFeb MarApr
Milestone trend chart. The 45° diagonal is "today"; a milestone is delivered where its line meets it.

Worked example

Go-live milestone forecast at four monthly reports: 1 Sep, 15 Sep, 1 Oct, 15 Oct.

Elapsed between reports: 30 days each (3 intervals = 90 days) Total forecast slip: 1 Sep → 15 Oct = 44 days Slip rate = 44 / 90 = 0.49 days lost per day elapsed Extrapolated: to close a 44-day gap at zero recovery rate is impossible; at the current rate the milestone recedes a further 0.49 d per elapsed day, so the forecast finish converges only when slip rate falls below 1.0 and the line crosses the diagonal. Current trajectory: no convergence.
Exam trap. A falling line is not automatically good news. Ask what changed: descoping, a re-baselined milestone definition, or a genuine acceleration. MTA is a trend indicator, not a measure of performance — use EVM (B1) for that.

A6 Duration estimating techniques

Primary 4.5.4 Time · KCI 4.5.4.2 Determine the work effort and duration of activities

Where a duration number comes from before it enters the network.

Four techniques, in ascending order of effort and accuracy. Exams usually give you the data for one and ask you to apply it, or describe a situation and ask which technique fits.

Analogous duration = past duration × scaling factor top-down, fast, low accuracy Parametric duration = quantity × productivity rate needs a validated rate Bottom-up duration = sum of work-package durations highest effort and accuracy Three-point see A3 quantifies the uncertainty

Worked example — all four on the same activity

Activity: migrate 240 customer data tables to a new core platform.

Analogous Previous migration: 160 tables in 20 days. Scaling by volume: 20 × (240 / 160) = 30 days Parametric Validated rate: 1 engineer completes 4 tables per day. Team of 3. Effort = 240 / 4 = 60 engineer-days Duration = 60 / 3 = 20 days Bottom-up Simple tables 180 × 0.20 d = 36.0 engineer-days Complex tables 50 × 0.75 d = 37.5 engineer-days Reference data 10 × 2.00 d = 20.0 engineer-days Total effort = 93.5 engineer-days Duration at 3 engineers = 93.5 / 3 = 31.2 days Three-point on the bottom-up figure O = 26, M = 31, P = 46 t_e = (26 + 124 + 46) / 6 = 32.7 days σ = (46 − 26) / 6 = 3.3 days

The parametric answer is the outlier because its rate was calibrated on simple tables only. The spread across techniques is itself information: it tells you the estimate is sensitive to the complexity mix, which is exactly what the three-point range then quantifies.

Exam trap. Effort and duration are different quantities and the conversion is not always division. Duration = effort / (resources × availability), and availability is rarely 100% — a nominal 3-person team at 80% availability gives 2.4 effective engineers, not 3. Watch for questions that hand you effort in person-days and ask for elapsed calendar time.

B  Plan and control ICB4 4.5.10

All five methods in this group use one running example: a core-platform migration with BAC = €500,000 over 10 months, reported at the end of month 6.

B1 Earned value — core metrics

Primary 4.5.10 Plan and control · KCI 4.5.10.3 Control project performance against the project plan and take any necessary remedial actions Also 4.5.7 Finance · 4.5.4 Time

Whether you are ahead or behind, over or under, in one integrated set of numbers.

EVM compares three cumulative money figures at a single point in time. Planned value is what you said you would have accomplished by now. Earned value is the budget of what you actually accomplished. Actual cost is what you spent doing it. Every other EVM number is derived from these three.

PV planned value budgeted cost of work scheduled (BCWS) EV earned value budgeted cost of work performed (BCWP) AC actual cost actual cost of work performed (ACWP) BAC budget at completion = total PV at the end Cost variance CV = EV − AC negative = overspent Schedule variance SV = EV − PV negative = behind Cost perf. index CPI = EV / AC below 1.0 = overspent Sched. perf. index SPI = EV / PV below 1.0 = behind Variance % CV% = CV / EV SV% = SV / PV
data date — month 6 CV = −40k SV = −30k PV → BAC 500k AC → EAC 574k EV 270k months cumulative cost 024 6810
The classic S-curve. EV below PV is the schedule gap; AC above EV is the cost gap. Both are measured vertically at the data date.

Worked example

At end of month 6: PV = 300,000 EV = 270,000 AC = 310,000 BAC = 500,000 CV = EV − AC = 270,000 − 310,000 = −40,000 overspent SV = EV − PV = 270,000 − 300,000 = −30,000 behind schedule CPI = EV / AC = 270,000 / 310,000 = 0.871 87.1 cents of value per euro spent SPI = EV / PV = 270,000 / 300,000 = 0.900 90% of planned progress CV% = −40,000 / 270,000 = −14.8% SV% = −30,000 / 300,000 = −10.0% % complete = EV / BAC = 270,000 / 500,000 = 54% % spent = AC / BAC = 310,000 / 500,000 = 62%

The project has produced 54% of the scope while consuming 62% of the budget, six months into a ten-month plan.

Exam trap. SV is expressed in money, not time — €30,000 behind does not mean any particular number of weeks late. That is exactly what earned schedule (B4) fixes. Also memorise the sign convention: everything is EV minus something, so negative is always bad, and both indices are EV over something, so below 1.0 is always bad.

B2 Forecasting — EAC, ETC, VAC, TCPI

Primary 4.5.10 Plan and control · KCI 4.5.10.4 Report on project progress Also 4.5.7 Finance

What the project will finally cost, what remains to spend, and how efficient you must become to still hit the number.

Four EAC formulas exist because they encode four different assumptions about the future. The examiner is usually testing whether you can justify which one applies, not just compute it.

EAC 1 — past variance was atypical EAC = AC + (BAC − EV) remaining work at budgeted rate EAC 2 — current cost performance continues EAC = BAC / CPI = AC + (BAC − EV) / CPI EAC 3 — cost and schedule pressure both continue EAC = AC + (BAC − EV) / (CPI × SPI) EAC 4 — bottom-up re-estimate EAC = AC + new ETC ETC = EAC − AC estimate to complete VAC = BAC − EAC negative = forecast overrun TCPI to BAC = (BAC − EV) / (BAC − AC) TCPI to EAC = (BAC − EV) / (EAC − AC)

Worked example

PV 300,000 EV 270,000 AC 310,000 BAC 500,000 CPI 0.871 SPI 0.900 Remaining work at budget = BAC − EV = 500,000 − 270,000 = 230,000 EAC 1 = 310,000 + 230,000 = 540,000 EAC 2 = 500,000 / 0.871 = 574,074 EAC 3 = 310,000 + 230,000 / (0.871 × 0.900) = 310,000 + 230,000 / 0.7839 = 603,415 Using EAC 2: ETC = 574,074 − 310,000 = 264,074 VAC = 500,000 − 574,074 = −74,074 forecast overrun of 14.8% TCPI to BAC = 230,000 / (500,000 − 310,000) = 230,000 / 190,000 = 1.211 TCPI to EAC = 230,000 / (574,074 − 310,000) = 230,000 / 264,074 = 0.871

TCPI to BAC of 1.211 says the remaining work must be delivered 21% more efficiently than budgeted, when performance to date has been 13% worse than budgeted. A swing of that size without a change in method or scope is not credible — which is the argument for re-baselining to the EAC.

Exam trap. TCPI to EAC always returns roughly the current CPI when the EAC was itself derived from CPI, so it tells you nothing new — its value is as a sanity check that the two are consistent. The meaningful figure is TCPI to BAC. Rule of thumb the examiners look for: if TCPI to BAC exceeds CPI by more than about 0.10, the baseline is no longer achievable.

B3 Percent-complete conventions

Primary 4.5.10 Plan and control · KCI 4.5.10.3 Control project performance against the project plan and take any necessary remedial actions

How EV gets a number attached to it in the first place, and why the choice changes your reported performance.

EV is only as honest as the rule used to credit partial progress. Each convention trades subjectivity against responsiveness.

ConventionCredit ruleBest forWeakness
0 / 100Nothing until complete, then full budgetShort packages inside one reporting periodUnderstates progress; jumpy
50 / 50Half on start, half on completionPackages spanning two periodsRewards starting, not finishing
20 / 8020% on start, 80% on completionLong packages with heavy back endArbitrary split
Milestone weightingFixed credit at each defined milestoneLong packages with verifiable gatesNeeds milestones defined up front
Units completeUnits delivered / total unitsRepetitive work — tables, tickets, metresAssumes units are equal effort
Percent completeManager's judgementNothing, ideallyFully subjective; the 90% syndrome
Apportioned effortTracks a linked base packageQA, PM overheadInherits the base package's errors
Level of effortEV = PV automaticallySupport functions with no outputSV always zero; distorts totals

Worked example

Four work packages, €100,000 each. WP1 finished, WP2 and WP3 started but unfinished, WP4 not started.

WP1 WP2 WP3 WP4 Total EV 0/100 100,000 0 0 0 100,000 50/50 100,000 50,000 50,000 0 200,000 20/80 100,000 20,000 20,000 0 140,000 Units complete 100,000 62,000 38,000 0 200,000 With AC = 230,000 across all four: CPI under 0/100 = 100,000 / 230,000 = 0.435 CPI under 50/50 = 200,000 / 230,000 = 0.870 CPI under 20/80 = 140,000 / 230,000 = 0.609

Same project, same spend, three CPI figures between 0.43 and 0.87. This is why the convention must be fixed in the baseline and applied consistently, and why comparing CPI across organisations is meaningless without knowing the rule.

Exam trap. Level of effort packages inflate the aggregate SPI toward 1.0 because their EV equals their PV by definition. If a question gives you an SPI that looks suspiciously healthy alongside a visibly late project, check whether LOE packages are diluting the total — the fix is to compute SPI on discrete-effort packages only.

B4 Earned schedule

Primary 4.5.10 Plan and control · KCI 4.5.10.3 Control project performance against the project plan and take any necessary remedial actions Also 4.5.4 Time

Schedule performance expressed in time units instead of money, and without the end-of-project distortion.

Instead of subtracting PV from EV vertically, you project the EV level horizontally onto the PV curve and read off the date at which that much value should have been earned. The gap between that date and today is the schedule variance in months.

ES = the time at which cumulative PV equals current EV = N + (EV − PVN) / (PVN+1 − PVN) N = last period where PV ≤ EV AT = actual time elapsed SV(t) = ES − AT schedule variance in time units SPI(t) = ES / AT IEAC(t) = PD / SPI(t) PD = planned duration
EV 270k ES 5.4 AT 6.0 project the EV level left onto the PV curve PV baseline EV months
Earned schedule reads horizontally, not vertically. The answer comes out in months.

Worked example

Baseline PV is linear at 50,000 per month over 10 months. EV = 270,000, AT = 6.0. Find N: PV at month 5 = 250,000 ≤ 270,000; PV at month 6 = 300,000 > 270,000 → N = 5 ES = 5 + (270,000 − 250,000) / (300,000 − 250,000) = 5 + 20,000 / 50,000 = 5.4 months SV(t) = 5.4 − 6.0 = −0.6 months about 13 working days behind SPI(t) = 5.4 / 6.0 = 0.900 IEAC(t) = 10 / 0.900 = 11.11 months forecast 1.1 months late Compare: SV = −30,000 tells you the size of the gap in money but not in time.
Exam trap. Classic SPI is mathematically forced back to exactly 1.0 at project completion, because EV and PV both converge on BAC no matter how late you finish. SPI(t) does not — a project delivered two months late still shows SPI(t) = 10/12 = 0.833 at handover. If a question mentions a late-stage project with SPI near 1.0, earned schedule is the expected answer.

B5 Variance thresholds and trend extrapolation

Primary 4.5.10 Plan and control · KCI 4.5.10.3 Control project performance against the project plan and take any necessary remedial actions

When a variance stops being noise and becomes a reportable exception, and where the trend is heading.

A single period's CPI is largely noise. Control is exercised on the cumulative index and its direction of travel, against tolerance bands agreed in the baseline. Thresholds are usually asymmetric and tighten as the project progresses, because the ability to recover falls as remaining work shrinks.

Cumulative index CPIcum = ΣEV / ΣAC the control figure Period index CPIperiod = EVperiod / ACperiod the leading indicator Threshold breach |variance %| > agreed tolerance → exception report Linear extrapolation forecast index = current + (slope × periods remaining) Recovery test required CPI = TCPI to BAC; feasible only if within reach of the best period CPI achieved so far
1.00 1.05 0.95 0.87 tolerance band ±5% CPI trend 0.79 by month 8 if unchecked SPI first breach 123 456 reporting month
Index trend against a tolerance band. The breach point, not the current value, is where control should have been exercised.

Worked example

CPI_cum by month: 1.00, 0.98, 0.95, 0.93, 0.90, 0.871 Tolerance: cost variance beyond ±5% requires an exception report. First breach: month 3, CPI 0.95 — exactly at the −5% limit. Slope over months 3–6 = (0.871 − 0.95) / 3 = −0.0263 per month Extrapolated to month 8 = 0.871 + (−0.0263 × 2) = 0.818 Forecast at that CPI: EAC = 500,000 / 0.818 = 611,000 Recovery feasibility Required from here: TCPI to BAC = 1.211 Best period CPI achieved so far: 1.00 (month 1) Gap between required and best-ever = 0.21 → not achievable without a change in scope, method or baseline. Escalate rather than promise recovery.
Exam trap. Do not extrapolate from cumulative indices alone — they lag, because early good periods keep dragging the average up. The period index turns first. A question that gives both period and cumulative figures is usually testing whether you notice that the period CPI has already fallen below the cumulative one, which means the cumulative figure is still falling.

B6 Change request impact quantification

Primary 4.5.10 Plan and control · KCI 4.5.10.5 Assess, get agreement on and implement project changes Also 4.5.7 Finance · 4.5.3 Scope

What a proposed change actually costs once schedule, float and risk are priced in, and which pot of money pays for it.

A change request is priced across four channels, not one. Direct effort and materials are the visible part. Schedule impact is only the portion of added duration that survives the float already in the path. Risk impact is the movement in expected monetary value caused by the change. Time-related costs then convert any surviving delay into money. The funding decision is separate from the pricing and is where most marks are lost.

Direct cost Σ(effort × rate) + materials Net delay max(0, added duration − total float on that path) Time-related cost net delay × daily standing cost Risk delta ΔEMV = (p₁ × i₁) − (p₀ × i₀) Total change value direct + time-related + ΔEMV Cumulative ratio Σ approved change value / original BAC Funding rule realised known risk → contingency reserve new or altered scope → management reserve or baseline change
Activity as baselined 8 days work 6 days total float project finish as baselined With the change applied 8 + 10 = 18 days work 4 days net delay, the only part that is priced float absorbs 6 of the 10 added days — it does not absorb the cost of the work
Ten days of added duration against six days of float. Four days extend the project; the other six consume the buffer that protected every downstream path.

Worked example

Change request: add a regulatory reporting module. Direct cost Effort 120 h × 85/h = 10,200 Licence and materials = 3,500 Direct total = 13,700 Schedule Added duration on the affected path 10 days Total float available on that path 6 days Net delay = max(0, 10 − 6) = 4 days Standing cost 1,900/day × 4 = 7,600 Risk Integration failure, before: 0.10 × 40,000 = 4,000 Integration failure, after: 0.25 × 40,000 = 10,000 ΔEMV = 6,000 Total change value 13,700 + 7,600 + 6,000 = 27,300 Funding this is new scope, not a realised known risk, so contingency may not be used. It needs management reserve or a baseline change. Cumulative change ratio Approved to date 41,000 + this 27,300 = 68,300 68,300 / 500,000 = 13.7% of original BAC
Exam trap. The float is the trap. Candidates add all ten days to the project finish; only four survive the float and only those four carry time-related cost. The reverse error is treating a fully float-absorbed change as free — the direct cost and the ΔEMV are still payable, and the float consumed was protecting every path downstream. Second: contingency covers risks that were identified and priced, not scope that has just been invented. Funding new scope from contingency is the single most common change-control error, and it hides the growth until the reserve is empty.

C  Finance ICB4 4.5.7

C1–C6 use one running appraisal: a platform investment of €400,000 at t=0 returning €120,000 a year for five years, appraised at a 10% discount rate.

C1 Time value of money and discount factors

Primary 4.5.7 Finance Also 4.3.1 Strategy

What a future euro is worth today, which is the foundation under every other appraisal method here.

A euro received in three years is worth less than a euro today, because today's euro can be invested. Discounting converts every future cash flow back to a common point in time so that flows arriving in different years can legitimately be added together.

Future value FV = PV × (1 + r)n Present value PV = FV / (1 + r)n Discount factor DFn = 1 / (1 + r)n Annuity factor AF = (1 − (1 + r)−n) / r for n equal annual flows Perpetuity PV = C / r flow forever Rule of 72 years to double ≈ 72 / (r in %)

Worked example

r = 10% DF₁ = 1 / 1.10¹ = 1 / 1.1000 = 0.9091 DF₂ = 1 / 1.10² = 1 / 1.2100 = 0.8264 DF₃ = 1 / 1.10³ = 1 / 1.3310 = 0.7513 DF₄ = 1 / 1.10⁴ = 1 / 1.4641 = 0.6830 DF₅ = 1 / 1.10⁵ = 1 / 1.6105 = 0.6209 PV of 120,000 in year 3 = 120,000 × 0.7513 = 90,158 Annuity shortcut for 5 equal flows: AF = (1 − 1.10⁻⁵) / 0.10 = (1 − 0.6209) / 0.10 = 0.3791 / 0.10 = 3.7908 PV of the whole stream = 120,000 × 3.7908 = 454,896 Check by summing the factors: 0.9091+0.8264+0.7513+0.6830+0.6209 = 3.7907 ✓
Exam trap. Be explicit about whether a flow arrives at the start or end of the period. Standard convention is end of period, so a year-1 flow is discounted once, not zero times. An investment made at t=0 is not discounted. Getting this off by one period changes NPV by roughly the discount rate.

C2 Net present value

Primary 4.3.1 Strategy · KCI 4.3.1.3 Develop and ensure the ongoing validity of the business / organisational justification Also 4.5.7 Finance

Whether an investment creates value in absolute money terms, after paying for the cost of capital.

NPV sums every discounted inflow and outflow across the appraisal period. A positive NPV means the investment beats the discount rate. It is the primary decision rule because it is additive across projects and expressed in currency, not percentages.

NPV = Σt=0n Ct / (1 + r)t Decision rule NPV > 0 accept NPV < 0 reject among mutually exclusive options, take the highest NPV
−400k 10999 908275 t=0yr 1 yr 2yr 3 yr 4yr 5 nominal 120k discounted at 10% Σ discounted inflows 454,896 − 400,000 = NPV 54,896
Each year's inflow shrinks as it is pushed further into the future. The shortfall between the pale and solid bars is the cost of capital.

Worked example

YearCash flowDF @ 10%Present valueCumulative PV
0−400,0001.0000−400,000−400,000
1120,0000.9091109,091−290,909
2120,0000.826499,174−191,735
3120,0000.751390,158−101,577
4120,0000.683081,962−19,615
5120,0000.620974,51154,896
NPV200,000—54,896—
NPV = +54,896 → accept Sensitivity: at r = 15%, AF = 3.3522 → PV = 402,264 → NPV = +2,264 at r = 20%, AF = 2.9906 → PV = 358,872 → NPV = −41,128

The undiscounted profit looks like €200,000. Discounting removes €145,104 of that — the price of tying up €400,000 for five years.

Exam trap. Sunk costs never enter an NPV. Money already spent is irrecoverable and cannot change a forward-looking decision, however painful. Conversely, opportunity costs — the value forgone by using a resource here rather than elsewhere — do enter, even though no cash moves.

C3 Internal rate of return

Primary 4.3.1 Strategy · KCI 4.3.1.3 Develop and ensure the ongoing validity of the business / organisational justification Also 4.5.7 Finance

The discount rate at which the investment exactly breaks even, expressed as a percentage return.

IRR is the r that drives NPV to zero. It is popular with boards because it is a single comparable percentage, and dangerous for the same reason: it ignores scale and assumes reinvestment at the IRR itself.

Definition solve Σ Ct / (1 + IRR)t = 0 Linear interpolation between two trial rates IRR ≈ r₁ + (NPV₁ / (NPV₁ − NPV₂)) × (r₂ − r₁) Decision rule IRR > hurdle rate accept MIRR corrects the reinvestment assumption using an explicit reinvestment rate for inflows and finance rate for outflows

Worked example

Because the inflows are equal, use the annuity factor directly: AF required = 400,000 / 120,000 = 3.3333 Five-year annuity factors: at 15%: (1 − 1.15⁻⁵) / 0.15 = 3.3522 at 16%: (1 − 1.16⁻⁵) / 0.16 = 3.2743 Interpolate: IRR = 15% + [(3.3522 − 3.3333) / (3.3522 − 3.2743)] × 1% = 15% + (0.0189 / 0.0779) × 1% = 15% + 0.24% = 15.24% Same answer from NPV trials: NPV at 15% = +2,264 NPV at 20% = −41,128 IRR ≈ 15% + [2,264 / (2,264 + 41,128)] × 5% = 15% + 0.26% = 15.26% Hurdle rate 10% → IRR exceeds it by 5.24 points → accept

The two interpolations differ slightly because NPV is a curve, not a line; the wider your trial rates, the larger the interpolation error. Bracket the true IRR tightly.

Exam trap. IRR breaks in three cases the examiners like. First, non-conventional cash flows — if the sign of the net flow changes more than once, there can be multiple IRRs or none. Second, mutually exclusive projects of different size: a small project with 40% IRR can create less value than a large one with 15%, so decide on NPV. Third, IRR implicitly assumes interim cash is reinvested at the IRR itself, which is why MIRR exists.

C4 Payback and discounted payback

Primary 4.3.1 Strategy · KCI 4.3.1.3 Develop and ensure the ongoing validity of the business / organisational justification Also 4.5.7 Finance

How long the money is at risk before the investment returns it.

Payback is a liquidity and risk measure, not a profitability measure. It answers "when do I get my money back", ignores everything after that point, and in its simple form ignores the time value of money entirely.

Simple payback (even flows) = initial investment / annual net inflow Simple payback (uneven) = full years before recovery + (unrecovered amount / next year's flow) Discounted payback = same, using discounted cumulative flows

Worked example

Simple payback 400,000 / 120,000 = 3.333 years = 3 years 4 months Discounted payback (cumulative PV column from C2) End of year 4: cumulative PV = −19,615 — not yet recovered Year 5 discounted inflow = 74,511 Discounted payback = 4 + (19,615 / 74,511) = 4 + 0.263 = 4.26 years The 0.93-year gap between the two is the cost of capital made visible.

If the organisation applies a four-year payback rule, this investment passes on simple payback and fails on discounted payback. Which rule is written into the governance framework decides the outcome, not the arithmetic.

Exam trap. Payback is blind to everything beyond the payback point. Two options with identical 3.3-year payback can have radically different NPVs if one stops earning in year 4 and the other runs for fifteen. Never present payback as a standalone accept/reject rule — present it as a risk-exposure figure alongside NPV.

C5 Profitability index, benefit-cost ratio and ROI

Primary 4.3.1 Strategy · KCI 4.3.1.3 Develop and ensure the ongoing validity of the business / organisational justification Also 4.5.7 Finance

Value per unit of money invested — the measure you need when capital is rationed.

NPV tells you how much value is created; PI tells you how efficiently. When the constraint is a fixed capital budget rather than a hurdle rate, ranking by PI produces the highest total NPV within the constraint.

Profitability index PI = PV of future inflows / initial investment equivalently PI = 1 + (NPV / initial investment) Benefit-cost ratio BCR = PV of benefits / PV of costs Simple ROI ROI = (total benefit − total cost) / total cost Annualised ROI = simple ROI / number of years (approximation) Decision rule PI > 1.0 accept; under capital rationing rank by PI

Worked example

PI = 454,896 / 400,000 = 1.137 check: 1 + (54,896 / 400,000) = 1 + 0.137 = 1.137 ✓ BCR = 454,896 / 400,000 = 1.14 (costs all at t=0, so PV of costs = 400,000) Simple ROI = (600,000 − 400,000) / 400,000 = 50% over five years Annualised = 50% / 5 = 10% per year — note this ignores compounding and is therefore below the true IRR of 15.24% Capital rationing budget 500,000, three competing projects: NPV Investment PI Project X 54,896 400,000 1.137 Project Y 38,000 200,000 1.190 Project Z 61,000 500,000 1.122 Ranking by NPV alone picks Z: total NPV = 61,000 Ranking by PI picks Y then X: 200,000 + 400,000 = 600,000 — over budget Feasible best: Y + partial, or Y alone plus reserve. Y + X is infeasible; Y alone = 38,000; Z alone = 61,000 → take Z.

PI ranks correctly only when the projects are divisible or the budget can be filled exactly. Where it cannot, you must test the feasible combinations against total NPV, which is the point of the last block above.

Exam trap. Simple ROI is not comparable to IRR and never should be presented alongside it without saying so. ROI has no time dimension, so a 50% return over five years and a 50% return over one year produce the same figure. Also watch the denominator: some organisations define ROI on total cost, others on net investment after residual value.

C6 Discount rate selection and WACC

Primary 4.5.7 Finance Also 4.3.1 Strategy

Where the r in every formula above actually comes from.

The discount rate represents the organisation's cost of capital plus, in most frameworks, a premium for project-specific risk. The weighted average cost of capital blends the cost of equity and the after-tax cost of debt in the proportions the organisation actually uses.

WACC = (E/V × Re) + (D/V × Rd × (1 − T)) E = market value of equity Re = cost of equity D = market value of debt Rd = cost of debt V = E + D T = corporate tax rate CAPM for the cost of equity Re = Rf + β(Rm − Rf) Rf = risk-free rate β = systematic risk (Rm − Rf) = market premium Risk-adjusted project rate = WACC + project risk premium

Worked example

Capital structure: 60% equity, 40% debt. Tax rate 20%. Cost of equity via CAPM: R_f = 3.5%, β = 1.2, market premium = 5.5% R_e = 3.5% + 1.2 × 5.5% = 3.5% + 6.6% = 10.1% Cost of debt R_d = 6.0% WACC = (0.60 × 10.1%) + (0.40 × 6.0% × (1 − 0.20)) = 6.06% + (0.40 × 4.8%) = 6.06% + 1.92% = 7.98% Project risk premium for a first-of-kind platform migration: +2.0% Discount rate applied = 7.98% + 2.0% ≈ 10% ← the rate used in C1–C5 Effect of getting it wrong: at 8% NPV = 120,000 × 3.9927 − 400,000 = +79,124 at 12% NPV = 120,000 × 3.6048 − 400,000 = +32,576 A four-point error moves NPV by 46,548 — 85% of the base-case NPV.
Exam trap. Debt is multiplied by (1 − T) because interest is tax-deductible; equity is not. Forgetting the tax shield overstates WACC. Second point examiners probe: WACC is the right rate only for projects with the same risk profile as the firm's existing business. A materially riskier project needs a higher rate, or you will systematically approve bad projects and reject good safe ones.

C7 Life-cycle costing and total cost of ownership

Primary 4.5.7 Finance · KCI 4.5.7.1 Estimate project costs Also 4.3.1 Strategy

What the thing costs across its whole life, not just what it costs to build.

LCC captures acquisition, operation, maintenance, upgrade and disposal. Two options with identical purchase prices routinely differ by 40% or more over a life cycle, and the difference usually sits in the run costs and the timing.

LCC = acquisition + operation + maintenance + upgrade + disposal − residual value Discounted LCC = Σ (cost in year t) / (1 + r)t Equivalent annual cost EACann = discounted LCC / annuity factor use this to compare options with different lives

Worked example — build vs subscribe

Cost elementBuild: nominalBuild: PV @10%Subscribe: nominalSubscribe: PV @10%
Acquisition / setup, t=0350,000350,00060,00060,000
Annual run, yrs 1–5300,000227,448650,000492,804
Major upgrade, yr 380,00060,104——
Decommission / exit, yr 520,00012,41840,00024,836
Total750,000649,970750,000577,640
Annual run, build: 60,000 × AF(10%,5) = 60,000 × 3.7908 = 227,448 Annual run, subscribe: 130,000 × 3.7908 = 492,804 Upgrade in year 3: 80,000 × 0.7513 = 60,104 Nominal totals are identical at 750,000. Discounted, subscribing is cheaper by 72,330 — 11% of the LCC.

The entire difference comes from timing. Building front-loads €350,000 to t=0 where no discount applies; subscribing spreads the same money across five discounted years. Nothing about the two options' quality has been assessed — only when the cash leaves.

Exam trap. When two options have different useful lives, comparing raw LCC totals is invalid. Convert both to equivalent annual cost, or extend both to a common horizon (lowest common multiple of the lives). A five-year option at €578k and an eight-year option at €790k cannot be compared directly: €578k/3.7908 = €152k per year against €790k/5.3349 = €148k per year, which reverses the ranking.

C8 Break-even analysis

Primary 4.3.1 Strategy · KCI 4.3.1.3 Develop and ensure the ongoing validity of the business / organisational justification Also 4.5.7 Finance

The volume at which a venture stops losing money, and how much headroom you have above it.

Contribution per unit = price − variable cost per unit Break-even units = fixed costs / contribution per unit Break-even revenue = fixed costs / contribution margin ratio Contribution margin % = contribution per unit / price Margin of safety = (expected volume − break-even volume) / expected volume Target-profit volume = (fixed costs + target profit) / contribution per unit
break-even 10,000 u revenue total cost fixed cost 180k loss profit 05,000 15,000 €
Break-even is where the revenue line crosses total cost, not where it crosses fixed cost.

Worked example

Fixed costs 180,000. Price 45 per unit. Variable cost 27 per unit. Contribution per unit = 45 − 27 = 18 Contribution margin = 18 / 45 = 40% Break-even units = 180,000 / 18 = 10,000 units Break-even revenue = 180,000 / 0.40 = 450,000 (check: 10,000 × 45 ✓) Expected volume 14,000 units: Margin of safety = (14,000 − 10,000) / 14,000 = 28.6% Profit = (14,000 × 18) − 180,000 = 252,000 − 180,000 = 72,000 Volume needed for a 90,000 profit: (180,000 + 90,000) / 18 = 15,000 units Sensitivity: a 10% price cut to 40.50 drops contribution to 13.50 new break-even = 180,000 / 13.50 = 13,333 units — up 33%

A 10% price move produced a 33% move in break-even volume. Contribution-based businesses are far more sensitive to price than to volume, which is why discounting decisions belong at governance level.

Exam trap. Costs must be split into fixed and variable before you start, and semi-variable costs must be decomposed — typically with the high-low method: variable rate = (cost at high volume − cost at low volume) / (high volume − low volume). Questions often bury a stepped fixed cost (a second shift, a second server tier) that jumps at a volume threshold, which creates two break-even points.

C9 Cash flow forecasting and the funding requirement

Primary 4.5.7 Finance · KCI 4.5.7.3 Secure project funding

How much cash the project needs at its deepest point, and when.

The budget tells you the total; the cash flow profile tells you the peak exposure. The funding requirement is the largest cumulative negative position, and it is what the treasury function actually has to arrange.

Net cash flowt = inflowst − outflowst Cumulative position = Σ net cash flow up to t Funding requirement = |most negative cumulative position| Peak funding date = the period in which that low point occurs Buffer = funding requirement × (1 + management reserve %)
−320,000 peak funding requirement month 7 cash-positive, month 11 0 + month cumulative cash
The trough, not the total spend, sets the credit facility the project needs.

Worked example

MonthOutflowInflowNetCumulative
170,0000−70,000−70,000
270,0000−70,000−140,000
385,00030,000−55,000−195,000
485,00045,000−40,000−235,000
590,00070,000−20,000−255,000
695,00055,000−40,000−295,000
790,00065,000−25,000−320,000
860,00070,000+10,000−310,000
Peak———−320,000 in month 7
Funding requirement = 320,000, needed by end of month 7 With a 10% management reserve: facility to arrange = 320,000 × 1.10 = 352,000 Note the total project spend to month 8 is 645,000, but the facility needed is half that, because inflows arrive alongside the outflows. Cost of carry: 320,000 held for 4 months at 6% p.a. = 320,000 × 0.06 × (4/12) = 6,400 — a real project cost, often omitted
Exam trap. Cash flow is not the same as cost accrual. An invoice recognised in month 3 on 60-day terms leaves the bank in month 5, and the shift can move the peak funding date by a whole quarter. If a question gives payment terms, use them — that is the point of the question.

C10 Cost estimating techniques and estimate classes

Primary 4.5.7 Finance · KCI 4.5.7.1 Estimate project costs

How a cost number is produced, and how much to trust it at each stage.

Analogous cost = past cost × scaling factor −25% to +75% typical Parametric cost = quantity × unit rate needs a validated rate Bottom-up cost = Σ work-package costs −5% to +15% typical Three-point cost = (O + 4M + P) / 6 with σ = (P − O)/6 Vendor bid cost = quoted price + internal effort Scaling with capacity cost₂ = cost₁ × (capacity₂ / capacity₁)x x is typically 0.6–0.7 — economies of scale

Estimate accuracy narrows as design definition increases. Most frameworks define five classes, from an order-of-magnitude figure at concept to a definitive figure at execution readiness. The class, not the number, is what a governance board should be told.

StageTechniqueTypical rangeUse
ConceptAnalogous−30% / +50%Screening, portfolio triage
FeasibilityParametric−20% / +30%Business case
DefinitionMixed−15% / +20%Funding request
Design completeBottom-up−10% / +15%Baseline
ExecutionBottom-up + actuals−5% / +10%Control

Worked example — same scope, four techniques

Scope: migrate 240 tables (from A6), plus environment and testing. Analogous previous 160-table migration cost 520,000 520,000 × (240/160) = 780,000 Capacity-scaled analogous with x = 0.65 520,000 × (240/160)^0.65 = 520,000 × 1.2846 = 668,000 Parametric validated rate 2,900 per table 240 × 2,900 = 696,000 Bottom-up migration effort 93.5 person-days × 1,400 = 130,900 environment build = 95,000 test cycles (3 × 62,000) = 186,000 vendor licences = 240,000 PM and governance 12% of the above = 78,228 total = 730,128 Three-point on the bottom-up O = 640,000 M = 730,000 P = 950,000 Expected = (640,000 + 2,920,000 + 950,000) / 6 = 751,667 σ = (950,000 − 640,000) / 6 = 51,667 P80 figure ≈ 751,667 + 0.842(51,667) = 795,170

The linear analogous estimate is 12% above the capacity-scaled one, because doubling the volume of a migration does not double the fixed environment and tooling work. When a question gives you a scaling exponent, it is testing exactly that.

Exam trap. An estimate range is not the same as contingency. The range describes the estimator's uncertainty; contingency is money actually set aside against identified risk (C11). A −10%/+15% estimate with zero contingency is not a funded project. Also: parametric rates must come from the same organisation, technology and period, or they are analogous estimates wearing a parametric label.

C11 Contingency, management reserve and the cost baseline

Primary 4.5.7 Finance · KCI 4.5.7.2 Establish the project budget Also 4.5.11 Risk and opportunity

Which pot of money covers which kind of surprise, and who is allowed to release it.

The distinction is about authority as much as arithmetic. Contingency covers identified risks and sits inside the project manager's control. Management reserve covers unknown-unknowns and sits with the sponsor. Only one of the two is inside the cost baseline.

Cost baseline = work package estimates + contingency reserve Cost budget = cost baseline + management reserve Contingency covers known risks, released by the project manager, measured against EVM (it is part of PV and BAC) Management reserve covers unknown risks, released by the sponsor via change control, and sits outside BAC Contingency sizing = Σ EMV of identified risks (see D4) or = P80 estimate − P50 estimate (from Monte Carlo, D5)

Worked example

Work package estimates (bottom-up) 730,000 Contingency: sum of risk EMVs + 68,000 --------- Cost baseline = BAC 798,000 Management reserve at 8% of baseline + 63,840 --------- Total cost budget 861,840 Alternative sizing from Monte Carlo: P50 = 751,000 P80 = 812,000 Contingency = 812,000 − 751,000 = 61,000 Effect on EVM. When a risk fires and 40,000 of contingency is drawn: AC rises by 40,000 immediately. EV does not rise, because no additional scope was completed. → CPI falls. Contingency draw always shows as cost overrun in EVM unless the contingency was distributed into the affected packages. When management reserve is released instead: BAC and the baseline are formally increased through change control, so PV, EV and BAC all move together and CPI is not distorted.
Exam trap. Management reserve is not in BAC. A question giving you "budget 861,840, of which 63,840 management reserve" and asking for EAC expects BAC = 798,000. Second trap: contingency is not a percentage plucked from air — if a question describes a risk register with probabilities and impacts, it wants an EMV-derived figure, not "10% of budget".

C12 Inflation and currency exposure

Primary 4.5.7 Finance Also 4.5.11 Risk and opportunity

Keeping cash flows and discount rates in the same money, and sizing the exchange-rate risk on cross-border work.

Fisher relationship (1 + nominal) = (1 + real) × (1 + inflation) real rate = ((1 + nominal) / (1 + inflation)) − 1 Consistency rule nominal cash flows → discount at the nominal rate real cash flows → discount at the real rate never mix the two Escalating a cost costyear n = costtoday × (1 + i)n Interest rate parity F = S × (1 + rquote) / (1 + rbase) FX exposure = contracted foreign amount × (worst rate − budget rate)

Worked example — inflation

Nominal discount rate 10%, expected inflation 3%. Real rate = (1.10 / 1.03) − 1 = 1.06796 − 1 = 6.796% (the approximation 10% − 3% = 7% is close but not exact; use the ratio) A cost of 100,000 in today's money, incurred in year 4: nominal cost = 100,000 × 1.03⁴ = 100,000 × 1.1255 = 112,551 discounted at nominal 10%: 112,551 × 0.6830 = 76,872 same flow in real terms: 100,000 × (1/1.06796⁴) = 100,000 × 0.7687 = 76,872 ✓ Both routes give the same answer. Mixing them — discounting a real 100,000 at the nominal 10% — gives 68,300, understating by 11%.

WORKED EXAMPLE — CURRENCY

A contract commits the project to pay USD 600,000 in twelve months. Budget rate 1.08 USD per EUR. Budgeted cost = 600,000 / 1.08 = 555,556 EUR Adverse scenario: USD strengthens to 1.00 Cost becomes = 600,000 / 1.00 = 600,000 EUR Exposure = 600,000 − 555,556 = 44,444 EUR (+8.0%) Forward rate via interest rate parity, EUR rate 3.0%, USD rate 4.5%: F = 1.08 × (1.045 / 1.030) = 1.08 × 1.01456 = 1.0957 Hedged cost = 600,000 / 1.0957 = 547,595 EUR Hedging locks in a cost 7,961 below the budget rate and removes the 44,444 downside. The residual risk is that the rate moves favourably and the hedge becomes an opportunity cost.
Exam trap. The approximation real ≈ nominal − inflation is only acceptable at low rates. At 20% nominal and 12% inflation it gives 8% against a true 7.14% — an 11% relative error that compounds over the appraisal period. Use the ratio form unless the question explicitly permits the approximation.

C13 Depreciation

Primary 4.5.7 Finance

How a capital asset's cost is spread across the periods that benefit from it — which changes reported profit, tax and therefore project cash flow.

Straight line annual charge = (cost − residual value) / useful life Reducing balance annual charge = net book value × rate Units of production charge = (cost − residual) × (units this period / total units) Sum of years' digits charge = (cost − residual) × remaining life / Σdigits Net book value = cost − accumulated depreciation Tax shield = depreciation charge × tax rate (a real cash benefit)

Worked example

Asset cost €240,000, useful life 5 years, residual value €40,000. Depreciable amount = €200,000.

YearStraight lineNBVReducing balance @30%NBV
140,000200,00072,000168,000
240,000160,00050,400117,600
340,000120,00035,28082,320
440,00080,00024,69657,624
540,00040,00017,28740,337
Total200,000—199,663—
Straight line = (240,000 − 40,000) / 5 = 40,000 per year Reducing balance year 1 = 240,000 × 0.30 = 72,000 year 2 = 168,000 × 0.30 = 50,400 Units of production, total expected output 500,000 units, year 1 actual 120,000 units: 200,000 × (120,000 / 500,000) = 48,000 Tax shield at 20% tax, year 1: straight line 40,000 × 0.20 = 8,000 cash saved reducing balance 72,000 × 0.20 = 14,400 cash saved PV of the shield over 5 years at 10%: straight line 40,000 × 0.20 × 3.7908 = 30,326 reducing balance (14,400×0.9091)+(10,080×0.8264)+(7,056×0.7513) +(4,939×0.6830)+(3,457×0.6209) = 32,238

Accelerated depreciation moves the tax relief forward, so its present value is higher — €1,912 more here — even though the nominal total relief is almost identical.

Exam trap. Depreciation is a non-cash charge and must be added back when building a cash flow forecast. It enters the appraisal only through its tax effect. A question that hands you accounting profit and asks for NPV expects: cash flow = profit after tax + depreciation.

D  Risk and opportunity ICB4 4.5.11

D1–D7 use one register of five risks on the €730,000 migration from C10.

D1 Probability-impact matrix and risk scoring

Primary 4.5.11 Risk and opportunity · KCI 4.5.11.3 Assess the probability and impact of risks and opportunities

Ranking risks quickly when you have judgement but not reliable numbers.

Each risk gets a probability band and an impact band, usually on a 1–5 scale. The product is a risk score, and the matrix cell determines the response required. It is ordinal, not cardinal: a score of 20 is not twice as bad as a score of 10.

Risk score = probability rating × impact rating Typical bands 1 very low 2 low 3 medium 4 high 5 very high Zones score 1–4 accept, monitor score 5–9 manage, named owner score 10–14 mitigate actively, reserve allocated score 15–25 escalate, avoid or transfer Multi-criteria impact impact rating = max(cost, time, quality, reputation) or a weighted blend if the framework defines one
5 very high4 high 3 medium2 low1 very low 12345 impact probability R2 R1 R3 R4 score 1–4 accept    5–9 manage    10–14 mitigate    15–25 escalate
R2 scores 16 and must be escalated; R4 is a rare but severe risk sitting in a cell that ordinal scoring under-weights.

Worked example

IDRiskP ratingI ratingScoreZone
R1Vendor delivery slips3412Mitigate
R2Data quality defects4416Escalate
R3Key engineer leaves236Manage
R4Regulatory change155Manage
R5Vendor delivers early (opportunity)236Exploit
Ranking by score: R2 (16) > R1 (12) > R3 = R5 (6) > R4 (5) Ranking by EMV (D2, using the money values): R1 (30,000) > R2 (20,000) > R3 (16,000) > R4 (12,000) The two rankings disagree at the top. Ordinal scoring puts R2 first; monetary expectation puts R1 first, because R1's impact band (4) covers 100,000 while R2's band (4) covers only 40,000 in this register.
Exam trap. The matrix systematically mis-ranks low-probability, catastrophic risks like R4. A score of 5 sits it beside a routine staffing risk, yet its unmitigated impact could end the project. Whenever an exam register contains a 1×5 risk, the expected answer names the limitation of ordinal scoring and moves to EMV or a separate severity screen.

D2 Expected monetary value

Primary 4.5.11 Risk and opportunity · KCI 4.5.11.3 Assess the probability and impact of risks and opportunities Also 4.5.7 Finance

The average cost of a risk if you faced the same situation many times — the basis for pricing contingency.

EMV = probability × impact Convention threats carry a negative impact, opportunities positive (or: express both as costs, with opportunities negative) Aggregate total EMV = Σ EMV of all risks Post-response EMV = residual probability × residual impact Value of a response = EMV before − EMV after − cost of the response

Worked example

IDProbabilityImpactEMV
R1 Vendor delivery slips0.30100,00030,000
R2 Data quality defects0.5040,00020,000
R3 Key engineer leaves0.2080,00016,000
R4 Regulatory change0.10120,00012,000
R5 Vendor delivers early0.25−40,000−10,000
Total risk exposure——68,000
R1 EMV = 0.30 × 100,000 = 30,000 Total = 30,000 + 20,000 + 16,000 + 12,000 − 10,000 = 68,000 → the contingency reserve figure used in C11. Evaluating a response to R2. Proposed: a data profiling and cleansing sprint costing 15,000. Effect: probability falls 0.50 → 0.15, impact unchanged at 40,000. EMV before = 0.50 × 40,000 = 20,000 EMV after = 0.15 × 40,000 = 6,000 Reduction = 14,000 Cost = 15,000 Net value = 14,000 − 15,000 = −1,000 → not justified on EMV alone If the response also cut impact to 25,000: EMV after = 0.15 × 25,000 = 3,750 Net value = (20,000 − 3,750) − 15,000 = +1,250 → justified
Exam trap. EMV is an average over many repetitions, and a project runs once. A risk with EMV of €12,000 built from a 10% chance of €120,000 will, on the day, cost either nothing or €120,000 — never €12,000. This is why EMV sizes the reserve pool across a portfolio of risks but never justifies ignoring a single ruinous exposure.

D3 Decision tree analysis

Primary 4.5.11 Risk and opportunity · KCI 4.5.11.3 Assess the probability and impact of risks and opportunities

Choosing between options when each leads to uncertain outcomes, by rolling expected values back to the decision point.

Squares are decisions you control, circles are chance events you do not. You build the tree left to right and evaluate it right to left, replacing each chance node with its EMV and each decision node with the best branch.

At a chance node node value = Σ (branch probability × branch value) At a decision node node value = best branch value; prune the others Roll back evaluate from the right-hand ends toward the root EVPI expected value of perfect information = EV with perfect information − EV of the best single decision
Build in-house Buy from vendor works first time p = 0.60 rework needed p = 0.40 clean integration p = 0.80 integration issues p = 0.20 400,000 600,000 450,000 550,000 EMV = 0.6(400k) + 0.4(600k) = 480,000 EMV = 0.8(450k) + 0.2(550k) = 470,000 Decision: buy — expected cost 470,000 decision
Chance nodes collapse to their EMV; the decision node takes the better of the two. Cost minimisation, so lower wins.

Worked example

Branch A — build in-house Base cost 400,000. Works first time p = 0.60 → total 400,000 Rework needed p = 0.40 → total 400,000 + 200,000 = 600,000 EMV = (0.60 × 400,000) + (0.40 × 600,000) = 240,000 + 240,000 = 480,000 Branch B — buy from vendor Base cost 450,000. Clean integration p = 0.80 → total 450,000 Integration issues p = 0.20 → total 450,000 + 100,000 = 550,000 EMV = (0.80 × 450,000) + (0.20 × 550,000) = 360,000 + 110,000 = 470,000 Decision: buy. Expected saving 10,000. Sensitivity. The decision flips if the build rework probability falls below p where 400,000 + 200,000p = 470,000 200,000p = 70,000 → p = 0.35 So the recommendation is only 5 percentage points from reversing. That fragility, not the 10,000, is what a board needs to hear.
Exam trap. Branch probabilities at a chance node must sum to 1.0 and the branches must be mutually exclusive. Two other habits earn marks: always state whether the tree is minimising cost or maximising benefit (the "best" branch flips), and always run the sensitivity, because a near-tie decision presented as a firm recommendation is the kind of answer assessors mark down.

D4 Contingency sizing from aggregate exposure

Primary 4.5.11 Risk and opportunity · KCI 4.5.11.3 Assess the probability and impact of risks and opportunities Also 4.5.7 Finance

Converting a risk register into a defensible reserve figure.

Three routes exist, in ascending order of rigour. Which one is acceptable depends on the governance framework, but the EMV route is the minimum defensible standard at Level B.

1. Percentage rule contingency = baseline × fixed % fast, indefensible, ignores the actual risk profile 2. EMV aggregation contingency = Σ EMV of identified risks defensible, but assumes independence and gives a P50-ish figure 3. Simulated percentile contingency = Ptarget − P50 (from Monte Carlo, D5) handles correlation and gives an explicit confidence level Reserve drawdown curve plan the release profile: reserve should fall roughly in step with the closure of the risks it was sized against

Worked example — three routes on the same register

Cost baseline before contingency: 730,000 Route 1 flat 10% rule contingency = 73,000 no traceability to any specific risk Route 2 EMV aggregation (D2) contingency = 68,000 traceable line by line to R1–R5 Route 3 Monte Carlo at P80 (D5) P50 = 751,000, P80 = 812,000 contingency = 812,000 − 751,000 = 61,000 above the P50 estimate or 812,000 − 730,000 = 82,000 above the deterministic baseline The three answers differ by 21,000 — 29% of the smallest. State which route you used and against which base, or the number is not interpretable. Drawdown plan R4 regulatory window closes at month 3 → release 12,000 R2 data quality resolved at month 5 → release 20,000 if unused R1 vendor delivery confirmed at month 7 → release 30,000 if unused Reserve held to closure 16,000 (R3, staffing)
Exam trap. Summing EMVs assumes the risks are independent. They rarely are — vendor delay (R1) and data quality (R2) share a root cause in this register, so they will tend to fire together and the true aggregate exposure exceeds the sum of the individual EMVs. Correlation is the reason Monte Carlo exists; say so if the question gives you correlated risks.

D5 Monte Carlo simulation

Primary 4.5.11 Risk and opportunity · KCI 4.5.11.3 Assess the probability and impact of risks and opportunities Also 4.5.4 Time · 4.5.7 Finance

The full distribution of possible outcomes, not a single number, produced by sampling every uncertain input thousands of times.

You assign a probability distribution to each uncertain input, draw one random value from each, compute the model output, and repeat. The collected outputs form a distribution you can read percentiles from. It is the only method here that handles correlation and path convergence properly.

Common input distributions Triangular defined by O, M, P mean = (O + M + P) / 3 Beta-PERT defined by O, M, P mean = (O + 4M + P) / 6, less tail weight Normal defined by μ, σ symmetric, unbounded — rarely right for cost Uniform defined by min, max use when only the range is known Discrete for risk events: p of occurring, impact if it does Reading the output P50 median — equal chance of over or under P80 the common governance commitment level P90 used where overrun is severely penalised contingency = Ptarget − P50
50% 80% 90% 751k 812k 838k 640k contingency 61k total project cost cumulative probability
The output S-curve. Steep means low uncertainty; flat means the range of plausible outcomes is wide.

Worked example

Model inputs Migration effort triangular O 100k M 131k P 190k Environment build triangular O 80k M 95k P 140k Test cycles triangular O 150k M 186k P 260k Licences fixed 240k PM and governance 12% of the above, correlated to total R1 vendor delay discrete p 0.30, impact 100k R2 data quality discrete p 0.50, impact 40k Deterministic sum of most-likely values 131 + 95 + 186 + 240 = 652k, plus 12% = 730k ← the C10 baseline Simulation output, 10,000 iterations P10 = 698,000 P50 = 751,000 P80 = 812,000 P90 = 838,000 mean = 761,000 σ = 48,000 Two things to notice 1. P50 (751k) exceeds the deterministic baseline (730k) by 21,000. Right-skewed inputs and one-sided risk events push the median above the sum of most-likely values. This is why "sum the most likely figures" systematically underfunds projects. 2. Mean (761k) exceeds P50 (751k). In a right-skewed distribution the mean is always above the median, so a mean-based commitment already carries under 50% confidence. Contingency at P80 = 812,000 − 751,000 = 61,000
Exam trap. Correlation and merge bias. If two parallel schedule paths each have an 80% chance of finishing on time and are independent, the chance that both do is 0.8 × 0.8 = 64% — so the merge point is late more often than either path alone. Deterministic CPM cannot see this; Monte Carlo can. Any question about parallel paths converging on a milestone is asking about merge bias.

D6 Sensitivity analysis and tornado diagrams

Primary 4.5.11 Risk and opportunity · KCI 4.5.11.3 Assess the probability and impact of risks and opportunities Also 4.3.1 Strategy

Which input variables actually move the answer, so you know where to spend effort reducing uncertainty.

You vary one input at a time across its plausible range, holding the others at base case, and record the swing in the output. Sorting the swings by magnitude gives a tornado shape: the widest bar at the top is the variable that matters.

Swing = output at high input − output at low input Sensitivity / elasticity = (% change in output) / (% change in input) Switching value = the input value at which the decision reverses (e.g. the NPV = 0 point for that variable)
base NPV 54,896 Annual benefit ±20% −36k146k Project life ±1 year −20k123k Initial cost ±15% −5k115k Discount rate ±4 pts 33k / 79k ← lower NPV     higher NPV →
Ordered widest to narrowest. Benefit realisation is worth four times the analytical attention of the discount rate.

Worked example

Base case from C2: NPV = €54,896 on a €400,000 investment returning €120,000 a year for five years at 10%.

VariableLow case NPVHigh case NPVSwingRank
Annual benefit ±20%−36,083145,875181,9581
Project life ±1 year−19,612122,636142,2482
Initial cost ±15%−5,104114,896120,0003
Discount rate ±4 pts32,57679,12446,5484
Annual benefit −20% 96,000 × AF(10%,5) = 96,000 × 3.7908 = 363,917 NPV = 363,917 − 400,000 = −36,083 Elasticity of NPV to benefit % change in NPV = (−36,083 − 54,896) / 54,896 = −165.7% % change in input = −20% elasticity = 165.7 / 20 = 8.3 a 1% benefit shortfall costs 8.3% of NPV Switching values — where NPV hits zero Annual benefit: 400,000 / 3.7908 = 105,519 (−12.1% from base) Initial cost: 454,896 (+13.7% from base) Discount rate: the IRR, 15.24% (+5.2 points) Project life: between 4 and 5 years — the project does not break even until part way through year 5

The benefit stream needs only a 12% shortfall to destroy the case, while the cost estimate has 14% of headroom. That reverses where most projects put their assurance effort.

Exam trap. One-at-a-time sensitivity ignores interactions. If benefits fall because adoption is slow, the project life usually extends and costs usually rise too — three bars moving together, which the tornado cannot show. Sensitivity analysis identifies the variables worth simulating; Monte Carlo then handles them jointly. Present them as a pair, not as alternatives.

D7 Risk-adjusted schedule and cost forecasts

Primary 4.5.11 Risk and opportunity · KCI 4.5.11.3 Assess the probability and impact of risks and opportunities Also 4.5.10 Plan and control

Folding quantified risk back into the committed dates and numbers.

Risk-adjusted cost = deterministic estimate + contingency at the agreed confidence level Risk-adjusted duration = deterministic critical path + schedule contingency (buffer) at the agreed level Expected delay = Σ (probability × delay impact) Commitment level state the percentile: "P80 of 812,000" not "812,000"

Worked example

Cost Deterministic baseline (C10) 730,000 Contingency at P80 (D5) + 82,000 Risk-adjusted cost commitment = 812,000 (P80) Management reserve, sponsor-held + 63,840 Total authorised budget = 875,840 Schedule Deterministic critical path 12.0 months Schedule risks: R1 vendor delay p 0.30, impact 2.0 months → 0.60 R2 data quality p 0.50, impact 0.8 months → 0.40 R3 key engineer p 0.20, impact 1.5 months → 0.30 R5 early delivery p 0.25, impact −0.5 months → −0.125 Expected delay = 0.60 + 0.40 + 0.30 − 0.125 = 1.175 months Expected duration = 12.0 + 1.18 = 13.2 months Simulated P80 duration = 14.1 months Schedule buffer to commit at P80 = 14.1 − 12.0 = 2.1 months What to publish Internal working target 12.0 months / 730,000 (P30–P40) Committed external date 14.1 months / 812,000 (P80) The gap between them is the buffer, and it must be visible to the sponsor and invisible to the delivery teams.
Exam trap. Never add cost contingency and schedule contingency as if they were independent choices — a delay usually costs money (time-related overheads, extended team) and a cost problem usually costs time. Double-counting is as common an error as omission: if your cost model already contains R1's €100,000 impact and your schedule model already contains R1's two months, and the two months are separately priced at €60,000 of standing costs, you have counted part of R1 twice.

D8 Probability fundamentals

Primary 4.5.11 Risk and opportunity · KCI 4.5.11.3 Assess the probability and impact of risks and opportunities

The arithmetic underneath every method in this group.

Complement P(not A) = 1 − P(A) Independent AND P(A and B) = P(A) × P(B) General AND P(A and B) = P(A) × P(B | A) Mutually excl. OR P(A or B) = P(A) + P(B) General OR P(A or B) = P(A) + P(B) − P(A and B) At least one P(≥1 of n) = 1 − Π(1 − pi) Expected value E[X] = Σ pixi Bayes P(A | B) = P(B | A) × P(A) / P(B)

Worked example

At least one risk fires, using R1–R4 as independent: P(none fires) = (1−0.30)(1−0.50)(1−0.20)(1−0.10) = 0.70 × 0.50 × 0.80 × 0.90 = 0.252 P(at least one) = 1 − 0.252 = 0.748 Intuition check: no single risk exceeds 50%, yet a 75% chance that something fires. This is why contingency exists at portfolio level. Both parallel paths on time (merge bias, D5): P(path 1 on time) = 0.80, P(path 2 on time) = 0.80 P(milestone on time) = 0.80 × 0.80 = 0.64 With three parallel paths: 0.80³ = 0.512 Conditional: R2 data quality is twice as likely if R1 vendor delay fires, because the vendor's data extracts drive the quality issue. P(R1) = 0.30, P(R2 | R1) = 0.80, P(R2 | not R1) = 0.37 P(R2) = (0.30 × 0.80) + (0.70 × 0.37) = 0.24 + 0.259 = 0.499 ✓ P(both) = 0.30 × 0.80 = 0.24 If independent, P(both) would be 0.30 × 0.50 = 0.15. Correlation raises the joint exposure by 60%. Bayes: a schedule health check flags 90% of truly-late projects and falsely flags 20% of healthy ones. 30% of projects are truly late. P(late | flagged) = (0.90 × 0.30) / [(0.90 × 0.30) + (0.20 × 0.70)] = 0.27 / (0.27 + 0.14) = 0.27 / 0.41 = 0.659 A flag means a 66% chance of a real problem, not 90%.
Exam trap. Adding probabilities that are not mutually exclusive. P(R1 or R2) is not 0.30 + 0.50 = 0.80; it is 0.30 + 0.50 − 0.24 = 0.56 using the correlated joint probability above. Any time a question puts "or" between two events that can both happen, the general OR rule applies.

E  Quality ICB4 4.5.6

E1–E7 use the migration's testing data: 450 defects found across 240 migrated tables.

E1 Cost of quality

Primary 4.5.6 Quality · KCI 4.5.6.1 Develop and monitor the implementation of and revise a quality management plan for the project Also 4.5.7 Finance

What quality actually costs, split into money spent preventing problems and money spent because of them.

The PAF model divides quality cost into four categories, grouped into conformance and non-conformance. The governing insight is that prevention is the cheapest category and external failure is the most expensive, typically by an order of magnitude.

Cost of conformance Prevention training, standards, reviews, tooling, design quality Appraisal testing, inspection, audits, verification Cost of non-conformance Internal failure rework, scrap, retesting — found before delivery External failure incidents, penalties, remediation, reputation — after Total CoQ = prevention + appraisal + internal failure + external failure CoQ ratio = total CoQ / total project cost 1-10-100 rule a defect costs 1 to prevent, 10 to fix in test, 100 to fix in production

Worked example

CategoryTypeCost% of CoQ
Prevention — standards, data profiling, reviewsConformance40,0008%
Appraisal — three test cyclesConformance90,00018%
Internal failure — rework of failed migrationsNon-conformance120,00024%
External failure — post-go-live incidentsNon-conformance250,00050%
Total cost of quality—500,000100%
Conformance = 40,000 + 90,000 = 130,000 (26%) Non-conformance = 120,000 + 250,000 = 370,000 (74%) CoQ ratio = 500,000 / 730,000 project cost = 68% Business case for shifting spend Proposal: triple prevention spend, 40,000 → 120,000, targeting the data mapping defects that drive most external failures (see E5). Expected effect: external failure falls 60%, internal failure falls 40%. Prevention 40,000 → 120,000 +80,000 Appraisal 90,000 → 90,000 0 Internal failure 120,000 → 72,000 −48,000 External failure 250,000 → 100,000 −150,000 --------- New total CoQ = 382,000 −118,000 Return on the prevention investment = 118,000 / 80,000 = 2.5×
Exam trap. Appraisal is a conformance cost, not a failure cost — testing is something you choose to do, not something a defect forces on you. The rework triggered by a test finding is internal failure. Questions frequently mis-file test execution as failure cost to see whether you catch it.

E2 Statistical process control

Primary 4.5.6 Quality · KCI 4.5.6.3 Verify the achievement of project quality objectives and recommend any necessary corrective and/or preventive actions

Distinguishing normal process variation from a real change that needs investigating.

Control limits describe what the process actually does when nothing unusual is happening. They are calculated from the process data, not set from requirements. A point outside them, or a non-random pattern inside them, signals a special cause.

Individuals chart UCL = μ + 3σ LCL = μ − 3σ X-bar chart UCL = x̄̄ + A₂R̄ LCL = x̄̄ − A₂R̄ A₂ depends on subgroup size: n=3 → 1.023, n=4 → 0.729, n=5 → 0.577, n=6 → 0.483 R chart UCL = D₄R̄ LCL = D₃R̄ Out-of-control signals 1. any point beyond 3σ 2. seven consecutive points on one side of the mean (rule of seven) 3. seven consecutive points trending up or down 4. two of three consecutive points beyond 2σ on the same side 5. any non-random pattern — cycles, hugging the centre line
UCL 12.81 x̄̄ 12.00 LCL 11.19 out of control run of 7 above the mean — special cause before the breach batch number minutes per batch
The run of seven points above the mean is the earlier and more actionable signal; the limit breach merely confirms it.

Worked example

Migration batch processing time, subgroups of n = 5. Grand mean x̄̄ = 12.00 minutes. Mean range R̄ = 1.40 minutes. A₂ = 0.577. UCL = 12.00 + (0.577 × 1.40) = 12.00 + 0.808 = 12.81 minutes LCL = 12.00 − 0.808 = 11.19 minutes Batch 13 recorded 13.05 minutes → above UCL → special cause, investigate before continuing. But batches 7–13 were all above the mean: P(7 consecutive on one side by chance) = (0.5)⁷ = 0.0078 → less than a 1 in 128 chance. The process had already shifted at batch 7, six batches before the limit breach was visible. Estimating σ from R̄ σ ≈ R̄ / d₂, d₂ = 2.326 for n = 5 σ ≈ 1.40 / 2.326 = 0.602 minutes — needed for E3
Exam trap. Control limits and specification limits are unrelated. Control limits come from the process (what it does); specification limits come from the customer (what is required). A process can be perfectly in control and still produce nothing acceptable, or be out of control while every unit passes spec. Confusing the two is the classic SPC error and the whole point of E3.

E3 Process capability — Cp, Cpk and sigma level

Primary 4.5.6 Quality · KCI 4.5.6.3 Verify the achievement of project quality objectives and recommend any necessary corrective and/or preventive actions

Whether the process is good enough for the requirement, and whether it is centred on target.

Cp compares the spread of the process against the width of the specification, assuming perfect centring. Cpk drops that assumption and measures the distance to the nearer specification limit. Cp is the potential; Cpk is the reality.

Cp = (USL − LSL) / 6σ potential capability Cpk = min[ (USL − μ) / 3&sigma , (μ − LSL) / 3σ ] actual capability Reading the numbers Cpk < 1.00 process cannot meet spec Cpk = 1.00 3σ process, about 2,700 defects per million Cpk = 1.33 4σ process, the common industrial minimum Cpk = 1.67 5σ Cpk = 2.00 6σ, 3.4 DPMO allowing a 1.5σ long-term drift Sigma level z = 3 × Cpk DPMO = defects / (units × opportunities per unit) × 1,000,000 Yield = 1 − (DPMO / 1,000,000)

Worked example

Batch processing must complete between LSL = 10.0 and USL = 14.0 minutes. Process mean μ = 12.4 minutes, σ = 0.5 minutes (post-improvement). Cp = (14.0 − 10.0) / (6 × 0.5) = 4.0 / 3.0 = 1.333 Cpk = min[ (14.0 − 12.4) / (3 × 0.5) , (12.4 − 10.0) / (3 × 0.5) ] = min[ 1.6 / 1.5 , 2.4 / 1.5 ] = min[ 1.067 , 1.600 ] = 1.067 Cp of 1.333 says the process is narrow enough. Cpk of 1.067 says it is off-centre — sitting 0.4 minutes above the midpoint of 12.0, eating the upper margin. Recentring alone, without reducing variation: move μ from 12.4 to 12.0 → Cpk = 2.0/1.5 = 1.333 = Cp A pure adjustment, no variation reduction, and capability rises 25%. Defect rate at Cpk 1.067 z to the near limit = 3 × 1.067 = 3.20 P(Z > 3.20) = 0.000687 → 687 DPMO Yield = 1 − 0.000687 = 99.93% After recentring: z = 4.00, P = 0.0000317 → 32 DPMO, a 21× improvement DPMO on the migration itself 450 defects, 240 tables, 12 checkable fields per table = 450 / (240 × 12) × 1,000,000 = 450 / 2,880 × 1,000,000 = 156,250 DPMO ≈ 2.5 sigma. Nowhere near production-ready.
Exam trap. Cpk can never exceed Cp, and the two are equal only when the process is perfectly centred. If a calculation gives Cpk > Cp, you have made an arithmetic error. Second trap: a one-sided specification (a maximum response time with no minimum) has no Cp at all — only the relevant half of Cpk, sometimes written Cpu or Cpl.

E4 Sampling and sample size

Primary 4.5.6 Quality · KCI 4.5.6.3 Verify the achievement of project quality objectives and recommend any necessary corrective and/or preventive actions

How many items to inspect to make a defensible statement about the whole population.

Sample size for a proportion n = z² × p(1 − p) / e² z = confidence z-score p = expected proportion e = margin of error use p = 0.5 when unknown — it maximises n, the safe assumption Finite population correction nadj = n / (1 + (n − 1) / N) N = population size Sample size for a mean n = (zσ / e)² Acceptance sampling lot size → sample size n and acceptance number c accept the lot if defects in the sample ≤ c Confidence z-scores 90% → 1.645 95% → 1.960 99% → 2.576

Worked example

How many migrated records to verify? Population N = 2,400 reconciliation records. Want 95% confidence, ±5% margin of error, no prior estimate of the defect rate. n = 1.96² × 0.5 × 0.5 / 0.05² = 3.8416 × 0.25 / 0.0025 = 0.9604 / 0.0025 = 384.16 → 385 records Finite population correction: n_adj = 384.16 / (1 + (384.16 − 1) / 2,400) = 384.16 / (1 + 0.1597) = 384.16 / 1.1597 = 331.3 → 332 records Effect of tightening the margin of error ±10% → n = 0.9604 / 0.01 = 97 ±5% → n = 0.9604 / 0.0025 = 385 ±2.5% → n = 0.9604 / 0.000625 = 1,537 Halving the error quadruples the sample. Precision is expensive. Using a prior estimate. Earlier cycles suggest p ≈ 0.15: n = 3.8416 × 0.15 × 0.85 / 0.0025 = 0.4898 / 0.0025 = 196 A credible prior halves the sample. This is why pilot batches pay for themselves. Result interpretation. 332 records sampled, 41 defective. p̂ = 41 / 332 = 0.1235 standard error = √(0.1235 × 0.8765 / 332) = √0.000326 = 0.0181 95% CI = 0.1235 ± (1.96 × 0.0181) = 0.1235 ± 0.0354 = 8.8% to 15.9% defective across the full population On 2,400 records that is between 211 and 382 defects.
Exam trap. Sample size depends on the margin of error and confidence level, and barely at all on population size until the sample becomes a large fraction of it. The instinct that a bigger population needs a proportionally bigger sample is wrong: 385 works for a population of 10,000 and for 10,000,000. The finite population correction only bites when n approaches N.

E5 Pareto analysis

Primary 4.5.6 Quality · KCI 4.5.6.3 Verify the achievement of project quality objectives and recommend any necessary corrective and/or preventive actions

Finding the small number of causes responsible for most of the problem.

Method 1. count occurrences by cause category 2. sort descending 3. compute cumulative percentage 4. the categories reaching ~80% cumulative are the vital few Weighted Pareto sort by (frequency × cost per occurrence) instead of frequency alone, when impacts differ materially
18796 7143 281510 80% 41.6 62.9 78.7 mappingencoding ref datarounding timezonedupesother the vital few — 3 of 7 categories, 78.7% of defects
Bars are frequency, the line is cumulative percentage. The break point is where the line flattens, not exactly at 80%.

Worked example

Defect categoryCount%Cumulative %Cost eachTotal cost
Data mapping errors18741.641.634063,580
Encoding / charset9621.362.912011,520
Missing reference data7115.878.788062,480
Rounding / precision439.688.21,45062,350
Timestamp / timezone286.294.42607,280
Duplicates153.397.81902,850
Other102.2100.02102,100
Total450100——212,160
By frequency mapping, encoding, reference data = 78.7% of defects By cost mapping (63,580), reference data (62,480), rounding (62,350) = 188,410 / 212,160 = 88.8% of the cost The two lists differ. Encoding is the second most frequent defect but only the fifth most expensive; rounding is the fourth most frequent and the third most expensive, because each one requires a financial reconciliation to unwind. Fix priority by cost, not count.
Exam trap. The 80/20 split is an observed tendency, not a law — here it is 79/43. Never force the data to hit exactly 80%; report the actual cumulative figure. Second point examiners look for: a frequency Pareto and a cost-weighted Pareto can rank differently, and the cost-weighted one is the one that should drive action.

E6 Histograms, scatter plots and correlation

Primary 4.5.6 Quality · KCI 4.5.6.3 Verify the achievement of project quality objectives and recommend any necessary corrective and/or preventive actions

Seeing the shape of a distribution, and testing whether two variables actually move together.

Histogram frequency by value bucket; shows centre, spread and shape (bimodal usually means two processes mixed together) Correlation coefficient r = Σ(x − x̄)(y − ȳ) / √[ Σ(x − x̄)² × Σ(y − ȳ)² ] ranges −1 to +1; |r| > 0.7 usually called strong Coefficient of determination r² = proportion of variance explained Least-squares regression line y = a + bx b = Σ(x − x̄)(y − ȳ) / Σ(x − x̄)² a = ȳ − bx̄
table complexity score defects y = 0.28 + 1.71x r = 0.965 r² = 0.931 defects per table right-skewed — long upper tail
Scatter with fitted line and the matching histogram of defects per table. The skew is why mean and median differ (M1).

Worked example

Does table complexity predict defect count? Six sampled tables.

x complexityy defectsx−x̄y−ȳ(x−x̄)(y−ȳ)(x−x̄)²(y−ȳ)²
24−3.5−5.6719.8312.2532.11
36−2.5−3.679.176.2513.44
59−0.5−0.670.330.250.44
680.5−1.67−0.830.252.78
8152.55.3313.336.2528.44
9163.56.3322.1712.2540.11
Σ 33Σ 58——64.0037.50117.33
x̄ = 33 / 6 = 5.50 ȳ = 58 / 6 = 9.67 r = 64.00 / √(37.50 × 117.33) = 64.00 / √4,399.9 = 64.00 / 66.33 = 0.965 r² = 0.931 → 93% of the variation in defects is explained by complexity Regression line: b = 64.00 / 37.50 = 1.707 defects per complexity point a = 9.67 − (1.707 × 5.50) = 9.67 − 9.39 = 0.28 y = 0.28 + 1.71x Predicted defects for a complexity-7 table = 0.28 + (1.71 × 7) = 12.2 Use. With 50 complex tables remaining at an average complexity of 7, forecast defects = 50 × 12.2 = 610, which sizes the remaining test and rework effort far better than a flat average would.
Exam trap. Correlation is not causation, and it is also not slope. A steep regression line can have weak correlation and a shallow one strong correlation — r measures scatter around the line, b measures the line's gradient. Third point: never extrapolate the regression beyond the observed range of x; the relationship at complexity 20 is unknown.

E7 Defect density, removal efficiency and rework rate

Primary 4.5.6 Quality · KCI 4.5.6.3 Verify the achievement of project quality objectives and recommend any necessary corrective and/or preventive actions

Normalised quality metrics that let you compare across releases, teams and phases.

Defect density = defects / size (per KLOC, per table, per function point, per requirement) Defect removal efficiency DRE = defects found before release / (found before + found after) × 100 Phase containment = defects found in the phase they were injected / defects injected in that phase Rework rate = rework effort / total effort Defect escape rate = defects found in production / total defects Mean time to repair = total repair time / number of repairs

Worked example

Defect density 450 defects across 240 tables = 1.88 defects per table Split by complexity band: simple (180 tables) 148 defects → 0.82 per table complex ( 50 tables) 262 defects → 5.24 per table reference (10 tables) 40 defects → 4.00 per table Complex tables carry 6.4× the defect density of simple ones. Defect removal efficiency Found before go-live 450 Found in production 38 DRE = 450 / (450 + 38) × 100 = 450 / 488 × 100 = 92.2% Industry expectation for a regulated migration is 95%+, so the test strategy under-performed by roughly 3 points. Defects that a 95% DRE would have caught before go-live: total defects 488 × 0.95 = 463.6 → 14 more caught in test at a 1-10-100 cost ratio, 14 production defects at ~2,400 each versus ~240 each in test = 30,240 avoidable cost Rework rate Rework effort 142 person-days, total effort 930 person-days = 142 / 930 = 15.3% A rework rate above ~10% usually indicates a requirements or design problem, not a build problem — consistent with E5, where the top defect category is data mapping, a specification activity. Escape rate = 38 / 488 = 7.8% (the complement of DRE)
Exam trap. Defect density is meaningless without a stated size unit, and comparisons across projects require the same unit and the same defect definition. "1.88 defects per table" and "1.88 defects per KLOC" are not comparable quantities. Second trap: DRE can only be computed after a settling period in production — a DRE quoted on go-live day is always 100% and always wrong.

F  Resources ICB4 4.5.8

F1 Resource histograms and loading

Primary 4.5.8 Resources · KCI 4.5.8.4 Allocate and distribute resources according to defined need Also 4.5.4 Time

Whether the schedule you built is actually staffable with the people you have.

You sum each period's resource demand across all concurrently scheduled activities and plot it against available capacity. Peaks above the capacity line are over-allocations that the network alone cannot see.

Period demand = Σ (resource units required by each active activity) Over-allocation = period demand − available capacity, where positive Resource-days = demand × duration; the area under the histogram Peak-to-average = peak demand / mean demand; above ~1.5 signals a profile that will be expensive to staff
capacity 6 2 4 8 10 9 5 4 3 2 over-allocation: 11 resource-months above capacity month engineers required
Demand profile before levelling. The red segments are the work that has nowhere to go.

Worked example

Monthly demand: 2, 4, 8, 10, 9, 5, 4, 3, 2 engineers Available capacity: 6 engineers Total resource-months = 2+4+8+10+9+5+4+3+2 = 47 Mean demand = 47 / 9 = 5.22 engineers Peak demand = 10 Peak-to-average ratio = 10 / 5.22 = 1.92 — badly peaked Over-allocation: month 3: 8 − 6 = 2 month 4: 10 − 6 = 4 month 5: 9 − 6 = 3 total = 9 resource-months with nowhere to go Capacity available across the 9 months = 6 × 9 = 54 resource-months Demand = 47. The total capacity is sufficient; only the profile is wrong. That is the case where levelling works. If demand exceeded 54, no amount of levelling would help — you would need more people or less scope.
Exam trap. Always test total demand against total capacity before proposing levelling. Levelling redistributes work in time; it cannot create capacity. If the area under the histogram exceeds the area under the capacity line, the answer is more resource, reduced scope or a longer schedule — not levelling.

F2 Resource levelling and smoothing

Primary 4.5.8 Resources · KCI 4.5.8.4 Allocate and distribute resources according to defined need Also 4.5.4 Time

Two different ways of fixing an unstaffable profile, distinguished by whether the end date is allowed to move.

Levelling respects a hard resource constraint; delays activities as needed even if the critical path lengthens → end date can move; float can be consumed entirely → may create a resource-critical path different from the logical critical path Smoothing respects the end date; adjusts activities only within their available float → end date fixed; peaks reduced but not always eliminated Test can the peak be removed using float alone? yes → smoothing is sufficient no → levelling is required

Worked example

Same profile. Activities contributing to the month 3–5 peak: Act P 3 engineers, months 3–5, total float 0 critical, cannot move Act Q 3 engineers, months 4–5, total float 2 can shift Act R 2 engineers, month 4 only, total float 4 can shift Attempt smoothing first (end date must hold) Shift Q by 2 months → now months 6–7 Shift R by 4 months → now month 8 New profile: 2, 4, 5, 5, 6, 8, 7, 5, 2 Month 6 now peaks at 8 — still 2 over capacity, and R and Q have no float left. Smoothing alone is insufficient. Level (accept schedule extension) Push Q a further 2 months beyond its float, into months 8–9. New profile: 2, 4, 5, 5, 6, 6, 5, 6, 5, 3 over 10 months Peak = 6, within capacity. Peak-to-average = 6 / 4.7 = 1.28 (was 1.92) Cost: project extends from 9 to 10 months. Resource-critical path The logical critical path was P → ... → finish at month 9. After levelling, Q's forced delay drives the finish. Q is now on the resource-critical path even though its logical total float was 2. Any further delay to Q now delays the project one-for-one.
Exam trap. After levelling, the original float figures are void. An activity shown with 2 days of total float in the logic network may have zero effective float once a resource constraint binds it. Questions that ask "what is the float of activity Q after levelling" are testing this: the answer is not the number from the CPM pass.

F3 Capacity, utilisation, FTE and man-months

Primary 4.5.8 Resources · KCI 4.5.8.5 Evaluate resource usage and take any necessary corrective actions

Converting between headcount, effort and elapsed time without double-counting.

FTE = contracted hours / standard full-time hours Available hours = FTE × working days × hours per day × availability % Utilisation = billable or project hours / available hours Duration = effort / (resources × availability) Man-months = headcount × elapsed months Two distinct figures — never conflate them Management effort = the project manager's own time on the project Execution effort = total team effort ≈ average headcount × duration

Worked example

Availability Standard year: 260 working days Less public holidays −12 Less annual leave −25 Less training and sickness −8 Productive days per FTE = 215 Applying a 15% deduction for line management, internal meetings and administration not chargeable to the project: Project-available days = 215 × 0.85 = 182.75 per FTE per year = 15.2 days per month, not the nominal 21.7. Effective availability = 182.75 / 260 = 70% Duration from effort Effort required 93.5 person-days, nominal team of 3. Naive: 93.5 / 3 = 31.2 working days Realistic: 93.5 / (3 × 0.70) = 93.5 / 2.1 = 44.5 working days A 43% difference, entirely from availability. Man-months for a certification application Project ran 18 months, average team size 11. Execution effort = 11 × 18 = 198 man-months Management effort = the PM's own 18 months at 60% allocation = 18 × 0.60 = 10.8 man-months These are separate figures answering separate questions. Reporting 198 as "your management effort" overstates it by a factor of 18. Utilisation Engineer logged 1,340 project hours against 1,462 available hours (182.75 days × 8) Utilisation = 1,340 / 1,462 = 91.7% Sustained utilisation above ~85% leaves no absorption capacity for variation, so queues and delays grow non-linearly (see L4).
Exam trap. Effort is additive, duration is not. Two 10-day activities running in parallel are 20 person-days of effort and 10 days of duration. And adding people to a late activity does not divide its duration proportionally — communication overhead grows with n(n−1)/2 (J1), so the marginal person contributes less than the last.

F4 Learning curve

Primary 4.5.8 Resources Also 4.5.4 Time

How unit effort falls as cumulative volume doubles — essential for repetitive work like migrations, rollouts and site deployments.

Learning rate the proportion of the previous effort required when cumulative output doubles. An 80% curve means the 2nd unit takes 80% of the 1st, the 4th 80% of the 2nd. Exponent b = ln(learning rate) / ln(2) 80% → b = ln(0.80)/ln(2) = −0.3219 90% → b = −0.1520 70% → b = −0.5146 Unit model Tn = T₁ × nb effort for the nth unit Cumulative average An = T₁ × nb average across n units Total effort = An × n
100h80h 64h51.2h unit 12 48 cumulative units produced — each label is a doubling 80% learning curve gains shrink in absolute terms
Each doubling cuts effort by the same proportion, so absolute savings shrink rapidly. Most of the benefit is captured early.

Worked example

First migration wave takes 100 hours. Assume an 80% learning curve. b = ln(0.80) / ln(2) = −0.2231 / 0.6931 = −0.3219 Unit model — effort for a specific wave Wave 1: 100 × 1^−0.3219 = 100.0 h Wave 2: 100 × 2^−0.3219 = 80.0 h Wave 4: 100 × 4^−0.3219 = 64.0 h Wave 5: 100 × 5^−0.3219 = 100 × e^(−0.3219 × ln 5) = 100 × e^(−0.3219 × 1.6094) = 100 × e^−0.5181 = 100 × 0.5957 = 59.6 h Wave 8: 100 × 8^−0.3219 = 51.2 h Cumulative average model — total for 8 waves A₈ = 100 × 8^−0.3219 = 51.2 h average per wave Total = 51.2 × 8 = 409.6 hours Without learning: 8 × 100 = 800 hours Saving: 800 − 409.6 = 390.4 hours, 49% Budgeting implication Estimating all 8 waves at the wave-1 rate overstates by 95%. Estimating them all at the wave-8 rate understates by 21%. Neither flat rate is defensible for repetitive work. Solving for the learning rate from actuals Wave 1 took 100 h, wave 4 took 72 h. 72 / 100 = 4^b → ln(0.72) = b ln(4) → b = −0.3285 / 1.3863 = −0.2370 learning rate = 2^−0.2370 = 84.8% — slower learning than assumed; re-forecast the remaining waves at 85%, not 80%.
Exam trap. Be explicit about which model the question wants. The unit model gives the effort for the nth item; the cumulative average model gives the running average and must be multiplied by n to get a total. They produce very different numbers from identical inputs — 51.2 hours for wave 8 versus 409.6 hours for all eight waves.

F5 Critical chain and buffer sizing

Primary 4.5.4 Time · KCI 4.5.4.3 Decide on schedule and stage approach Also 4.5.8 Resources

Removing the safety hidden inside individual task estimates and pooling it into explicit, managed buffers.

Critical chain assumes each task estimate already contains private safety that gets consumed anyway through Parkinson's law and student syndrome. You strip it out, schedule with aggressive durations, and place the recovered time in shared buffers at the points that actually need protecting.

Critical chain the longest path through the network after resource constraints are applied — not the same as the CPM critical path Aggressive duration typically the 50% confidence estimate Safe duration typically the 90% confidence estimate Safety removed = safe − aggressive, per task Project buffer protects the end date; placed at the chain's end 50% rule = 50% of the critical chain length SSQ method = √(Σ safetyi²) less inflationary on long chains Feeding buffer protects the chain from feeding-path delays Resource buffer an alert, not time, that a critical resource is due Control monitor buffer consumption against chain completion, in thirds: green 0–33%, amber 33–67%, red above 67%

Worked example

TaskSafe (90%)Aggressive (50%)Safety removedSafety²
Extract4.02.02.04.00
Transform5.02.52.56.25
Load3.01.51.52.25
Reconcile4.02.02.04.00
Sign-off2.01.01.01.00
Total18.09.09.017.50
Traditional schedule: 18.0 weeks, safety buried inside each task. Project buffer, 50% rule = 50% of the critical chain = 0.50 × 9.0 = 4.5 weeks Committed duration = 9.0 + 4.5 = 13.5 weeks (25% shorter than 18.0) Project buffer, SSQ method = √(4.00 + 6.25 + 2.25 + 4.00 + 1.00) = √17.50 = 4.18 weeks Committed duration = 9.0 + 4.18 = 13.2 weeks SSQ gives a smaller buffer because it assumes the task overruns are independent and will partly cancel — the same logic as PERT (A3). Feeding buffer on a non-chain path with 3.0 weeks of removed safety = 50% × 3.0 = 1.5 weeks, inserted where the path joins the chain Buffer control at week 7 Chain complete: 5.0 of 9.0 weeks = 55.6% Buffer consumed: 1.2 of 4.5 weeks = 26.7% Consumption is behind progress → green, no action. If instead buffer consumed were 3.4 of 4.5 = 75.6% at 55.6% chain progress → red, recovery plan required.
Exam trap. The critical chain is defined after resource levelling; the CPM critical path is defined by logic alone. They can be different sequences. Second point: buffer status is judged by comparing buffer consumed against chain completed, not against elapsed time. A project 60% through its buffer at 80% chain completion is healthy; the same buffer position at 30% completion is not.

F6 Resource competence gap scoring

Primary 4.5.8 Resources · KCI 4.5.8.5 Evaluate resource usage and take any necessary corrective actions

Where the team is short of the competence the work requires, how serious each shortfall is, and which shortfalls are single points of failure.

Required and actual competence are scored on the same scale for each competence the project needs, weighted by how critical that competence is to delivery. Gaps are floored at zero so that strength in one area cannot mathematically cancel a shortfall in another. Depth — how many people meet the required level — is tracked separately from level, because a team average conceals the single point of failure that actually threatens the schedule.

Gap gi = max(0, requiredi − actuali) Weighted gap G = Σ (wi × gi) Σwi = 1 Coverage Σ min(actuali, requiredi) / Σ requiredi Depth people at or above required level, per competence Single point depth = 1 at required level, or 0 with a live gap Closure cost min(train, hire, contract) subject to the date the competence is first needed
0 1 2 3 4 Structural analysis Contract law gap 2, depth 0 Cost control Stakeholder facilitation required actual
Only contract law carries a live gap, and it is the one competence where nobody on the team reaches the required level. Coverage alone would not have surfaced that.

Worked example

Competence Weight Required Actual Gap Weighted Structural analysis 0.35 4 3 1 0.35 Contract law 0.20 3 1 2 0.40 Cost control 0.25 4 4 0 0.00 Stakeholder facil. 0.20 3 3 0 0.00 ---- ------ 1.00 0.75 Coverage Σmin(actual, required) / Σrequired (3 + 1 + 4 + 3) / (4 + 3 + 4 + 3) = 11 / 14 = 78.6% Depth on contract law one person at level 1, nobody at level 3 → depth 0 — single point of failure Closure options, competence first needed in 8 weeks Train 8,000, ready in 12 weeks — misses the date Hire lead time 6 weeks + salary — meets the date, permanent cost Contract 40 days × 1,150 = 46,000 — meets the date, no tail Coverage rises to 100% under any option; only two of the three are feasible against the date, which is the actual decision.
Exam trap. Averaging competence across the team hides exactly what the analysis exists to find: an average of 3 can be one person at 5 and two at 2, and when the 5 leaves, the project stops. Score depth separately and never report a mean on its own. Second: floor every gap at zero. If negative gaps are allowed to net off, a team that is over-competent in cost control will appear to have no contract-law problem, and the arithmetic will have deleted the only finding that mattered.

G  Procurement ICB4 4.5.9

G1 Make-or-buy analysis

Primary 4.5.9 Procurement · KCI 4.5.9.1 Agree on procurement needs, options and processes Also 4.5.8 Resources

Whether to build a capability internally or acquire it, on a like-for-like financial basis.

Financial comparison discounted life-cycle cost of each option (C7) Indifference volume the volume at which the two options cost the same = (fixedmake − fixedbuy) / (variablebuy − variablemake) Non-financial factors strategic control, capability retention, exit cost, vendor concentration risk, speed to capability, regulatory accountability (cannot be outsourced)

Worked example

From C7, over five years at a 10% discount rate: Build PV = 649,970 Buy PV = 577,640 → buy is cheaper by 72,330 Indifference volume, treating the platform as processing transactions: Make: fixed 350,000 up front, variable 0.40 per transaction Buy: fixed 60,000 up front, variable 1.10 per transaction Indifference = (350,000 − 60,000) / (1.10 − 0.40) = 290,000 / 0.70 = 414,286 transactions Below 414,286 transactions → buy is cheaper Above 414,286 transactions → build is cheaper Forecast volume 350,000 over the period → buy, but with only 15% headroom before the decision flips. If volume growth exceeds forecast, revisit at the next gate. Weighted decision including non-financial factors
CriterionWeightMake scoreBuy scoreMake wtdBuy wtd
Five-year cost0.30681.802.40
Speed to capability0.20490.801.80
Regulatory control0.25952.251.25
Exit / switching cost0.15841.200.60
Internal capability retained0.10930.900.30
Total1.00——6.956.35
Financially, buy wins by 72,330. On weighted criteria, make wins 6.95 to 6.35, because regulatory control and exit cost together carry 40% of the weight. The decision therefore turns on the weighting, which is a governance judgement — not on the arithmetic.
Exam trap. Include the cost of managing the vendor on the buy side: contract management, service reviews, assurance and audit are real internal costs that make-or-buy comparisons routinely omit, and they typically run 5–15% of contract value. Also include exit cost on the buy side, even though it falls outside the appraisal period — that is exactly where lock-in hides.

G2 Contract type economics and the point of total assumption

Primary 4.5.9 Procurement · KCI 4.5.9.3 Contribute to the negotiation and agreement of contractual terms and conditions that meet project objectives Also 4.5.7 Finance

Who carries cost risk under each contract type, and where the buyer's exposure stops.

Risk gradient (seller risk highest on the left) FFP → FPIF → FP-EPA → CPIF → CPAF → CPFF → T&M buyer risk rises from left to right Incentive share ratio written buyer/seller, e.g. 70/30 seller's fee adjustment = (target cost − actual cost) × seller share underrun raises the fee, overrun cuts it Final price (FPIF) = actual cost + adjusted fee, capped at ceiling price Point of total assumption PTA = ((ceiling price − target price) / buyer share) + target cost above the PTA the seller absorbs 100% of every further cost

Worked example — fixed price incentive fee

Target cost 800,000 Target fee 80,000 Target price 880,000 Ceiling price 1,000,000 Share ratio 70 / 30 (buyer 70%, seller 30%) PTA = ((1,000,000 − 880,000) / 0.70) + 800,000 = (120,000 / 0.70) + 800,000 = 171,429 + 800,000 = 971,429 Case 1 — underrun. Actual cost 750,000 Underrun = 800,000 − 750,000 = 50,000 Seller's share = 50,000 × 0.30 = +15,000 Fee = 80,000 + 15,000 = 95,000 Final price = 750,000 + 95,000 = 845,000 Buyer saves 35,000 against target price; seller earns 15,000 more. Case 2 — overrun below the PTA. Actual cost 850,000 Overrun = 50,000; seller absorbs 30% = 15,000 Fee = 80,000 − 15,000 = 65,000 Final price = 850,000 + 65,000 = 915,000 (below ceiling ✓) Case 3 — at the PTA. Actual cost 971,429 Overrun = 171,429; seller absorbs 30% = 51,429 Fee = 80,000 − 51,429 = 28,571 Final price = 971,429 + 28,571 = 1,000,000 = ceiling ✓ Case 4 — above the PTA. Actual cost 1,050,000 Price is capped at the ceiling, 1,000,000 Seller's actual position = 1,000,000 − 1,050,000 = −50,000 loss Every euro of cost beyond 971,429 comes entirely out of the seller.
Exam trap. The PTA formula uses the buyer's share in the denominator, not the seller's. Using 0.30 instead of 0.70 gives 1,200,000 — above the ceiling, which is impossible and should be your check that the formula was applied correctly. Second point: the PTA is a warning line, not a protection. A seller heading past it has a strong incentive to cut quality or claim scope change, so the PTA is a contract-management trigger as much as a financial one.

G3 Weighted supplier scoring

Primary 4.5.9 Procurement · KCI 4.5.9.2 Contribute to the evaluation and selection of suppliers and partners

Converting a multi-criteria evaluation into a defensible single ranking.

Weighted score = Σ (criterion weight × supplier score) weights sum to 1.0 and are fixed before bids are opened Price scoring normalise so the lowest bid gets full marks: score = (lowest bid / this bid) × maximum points or the linear form: max × (1 − (bid − lowest) / lowest) Gate criteria pass/fail thresholds applied before weighting; a bid failing a gate is not scored at all

Worked example

CriterionWeightAlphaBetaGammaAlpha wtdBeta wtdGamma wtd
Price0.3010.08.37.13.002.492.13
Technical fit0.256981.502.252.00
Delivery capability0.207891.401.601.80
Regulatory / security0.155980.751.351.20
Reference strength0.106790.600.700.90
Total1.00———7.258.398.03
Price normalisation bids: Alpha 520,000, Beta 627,000, Gamma 730,000 Alpha = (520,000 / 520,000) × 10 = 10.0 Beta = (520,000 / 627,000) × 10 = 8.3 Gamma = (520,000 / 730,000) × 10 = 7.1 Result Beta 8.39 > Gamma 8.03 > Alpha 7.25 The cheapest bid finishes last, because it scores 5 on regulatory fit. Weight sensitivity — the question an assessor will ask Raise price weight from 0.30 to 0.50, taking 0.10 each from technical fit and regulatory: technical 0.15, regulatory 0.05 Alpha = (0.50×10) + (0.15×6) + (0.20×7) + (0.05×5) + (0.10×6) = 5.00 + 0.90 + 1.40 + 0.25 + 0.60 = 8.15 Beta = 4.15 + 1.35 + 1.60 + 0.45 + 0.70 = 8.25 Beta still wins, but by 0.10 instead of 1.14. The recommendation is robust in direction but not in margin. Say so.
Exam trap. Weights must be set and documented before bids are opened, or the model can be reverse-engineered to produce a chosen winner — a procurement governance failure, not just a methodological one. Second point: always run the weight sensitivity. A recommendation that flips under a plausible reweighting must be reported as a near-tie, not as a clear winner.

G4 Total cost of ownership bid comparison

Primary 4.5.9 Procurement · KCI 4.5.9.2 Contribute to the evaluation and selection of suppliers and partners Also 4.5.7 Finance

Comparing bids on their whole-life cost rather than their headline price.

Bid TCO = purchase price + implementation + integration + annual licence and support × years (discounted) + internal effort to run and govern + training + change costs + exit and migration cost − residual value Compare on discounted TCO, and where lives differ, on equivalent annual cost (C7)

Worked example

ElementAlphaBetaGamma
Headline bid price520,000627,000730,000
Integration effort (internal, t=0)180,00090,00060,000
Annual support, yrs 1–5, PV @10%341,172265,356227,448
Internal run and govern, PV151,632113,72494,770
Training and change (t=0)45,00060,00040,000
Exit / migration, yr 5, PV74,50837,25418,627
Five-year TCO (PV)1,312,3121,193,3341,170,845
Annual support: Alpha 90,000 × AF(10%,5) 3.7908 = 341,172 Beta 70,000 × 3.7908 = 265,356 Gamma 60,000 × 3.7908 = 227,448 Exit cost yr 5: Alpha 120,000 × DF₅ 0.6209 = 74,508 Ranking by headline price Alpha (520k) < Beta (627k) < Gamma (730k) Ranking by five-year TCO Gamma (1,171k) < Beta (1,193k) < Alpha (1,312k) The ranking reverses completely. Alpha's 210,000 price advantage is wiped out by 90,000 a year of support, higher integration effort and a 120,000 exit cost — total 142% of its headline saving. Combining with G3 Beta scored highest on weighted quality (8.39) and sits within 1.9% of the lowest TCO. Gamma is 22,489 cheaper over five years but scores 0.36 lower on quality. On a 1,171,000 base, 22,489 is 1.9% — inside the estimate's own margin of error, so the TCO difference is not decisive and the quality score should carry the decision.
Exam trap. Internal cost belongs in the TCO. A cheaper product that consumes 0.5 FTE more of internal administration is not cheaper. Questions that give you supplier prices and an internal effort figure are testing whether you include the second. Also: when TCO differences fall inside the estimating accuracy range (C10), say the comparison is inconclusive rather than declaring a winner on a rounding difference.

H  Scope ICB4 4.5.3

H1 WBS decomposition, the 100% rule and rollup

Primary 4.5.3 Scope · KCI 4.5.3.2 Structure the project scope

Breaking scope into countable pieces whose costs and durations roll up without gaps or double-counting.

100% rule each level of decomposition contains exactly 100% of the work of its parent — no more, no less, at every level Rollup parent value = Σ children values, applied bottom-up 8/80 rule work packages sized between 8 and 80 hours (a guideline) Control account the level at which EV is measured and a manager owns it Planning package scope known but not yet decomposed — must be decomposed before it can be baselined Code of accounts the hierarchical numbering that makes rollup traceable
1.0 Migration 730,000 1.1 Environment95,000 1.2 Data migration370,900 1.3 Test and cutover264,100 1.2.1 Extract88,400 1.2.2 Transform142,300 1.2.3 Load140,200 88,400 + 142,300 + 140,200 = 370,900 ✓ 95,000 + 370,900 + 264,100 = 730,000 ✓ every level sums exactly to its parent — the 100% rule
Rollup is only valid if the 100% rule holds at every level. A gap anywhere breaks the whole baseline.

Worked example

Rollup check, bottom-up 1.2.1 Extract 88,400 1.2.2 Transform 142,300 1.2.3 Load 140,200 1.2 subtotal = 370,900 1.1 Environment 95,000 1.2 Data migration 370,900 1.3 Test/cutover 264,100 1.0 total = 730,000 ✓ matches the C10 estimate Common failure — the missing 100% If project management effort (78,228 in C10) is not represented by a work package, the WBS rolls up to 651,772 while the budget is 730,000. The gap is 12% and it is invisible in the rollup because every level is internally consistent. The 100% rule fails against the scope, not against the arithmetic. Sizing check, 8/80 rule 1.2.2 Transform = 142,300 at a blended 1,400 per person-day = 101.6 person-days = 813 hours Far above 80 hours → decompose further before baselining. Split into 1.2.2.1 mapping rules, 1.2.2.2 build, 1.2.2.3 unit test. Control accounts Set at level 2 (1.1, 1.2, 1.3): three EVM measurement points, three named owners. Setting them at level 3 gives nine measurement points — better granularity, roughly triple the reporting effort.
Exam trap. The WBS is deliverable-oriented, not activity-oriented, and it contains work — not time and not organisational units. A "phase 2" node describing a period rather than a deliverable is a schedule artefact wearing a WBS label. Second trap: project management, quality assurance and change management are scope. If they are not in the WBS, they are not in the 100% and not in the baseline.

H2 Requirements prioritisation

Primary 4.5.2 Requirements and objectives · KCI 4.5.2.3 Prioritise and decide on requirements and acceptance criteria Also 4.5.3 Scope

Deciding what makes the cut when scope exceeds capacity, in a way you can defend.

MoSCoW Must / Should / Could / Won't this time discipline: Musts should be ≤ 60% of effort, or there is no room left to trade Weighted scoring priority = Σ(criterion weight × score) or value/effort = benefit score / effort estimate Kano classify each feature by how satisfaction responds to it: Must-be absence causes dissatisfaction, presence is neutral One-dimensional satisfaction rises linearly with fulfilment Attractive presence delights, absence is not missed Indifferent no effect either way Reverse presence causes dissatisfaction Cost of delay / WSJF = cost of delay / job duration
must-be one-dimensional attractive indifferent satisfied dissatisfied not implemented fully implemented
Must-be features buy no credit when present but cost heavily when absent. Attractive features are where discretionary effort earns most.

Worked example

RequirementMoSCoWKanoBenefitEffort (d)Value / effortRank
Regulatory audit trailMustMust-be9180.505
Automated reconciliationMustOne-dim.10220.456
Bulk re-run toolingShouldAttractive871.142
Migration dashboardShouldAttractive751.401
Self-service rollbackCouldAttractive661.003
Custom report builderCouldIndifferent3140.217
Legacy UI themingWon'tIndifferent290.22—
MoSCoW discipline check Must effort = 18 + 22 = 40 days Total in-scope effort (excluding Won't) = 72 days Musts = 40 / 72 = 56% — inside the 60% guideline, so there is genuine trading room. Above 60%, MoSCoW stops functioning as a prioritisation tool and becomes a wish list. The two rankings disagree, and both are right Value/effort ranks the dashboard first (1.40). MoSCoW ranks it third tier. The reconciliation requirement ranks last on value/effort (0.45) and first on MoSCoW. Resolution: MoSCoW governs what ships; value/effort governs the order within each MoSCoW band. Musts are not optional however poor their ratio, because the Kano classification says their absence causes active dissatisfaction. Kano insight Custom report builder is Indifferent and costs 14 days — 19% of in-scope effort for a feature nobody's satisfaction responds to. Cut it and the two Attractive items both fit.
Exam trap. "Won't" means won't this time, not "never". Deleting Won't items from the backlog loses the record of what was consciously deferred, which is exactly what change control needs later. Second point: Kano classification decays — today's Attractive feature is next year's Must-be, so a classification more than a year old should be re-tested.

H3 Size estimating — function points and story points

Primary 4.5.4 Time · KCI 4.5.4.2 Determine the work effort and duration of activities Also 4.5.3 Scope

Measuring the size of software scope in a unit that is independent of who builds it and how.

Function point counting Count five component types and weight each as low / average / high: EI external inputs 3 / 4 / 6 EO external outputs 4 / 5 / 7 EQ external inquiries 3 / 4 / 6 ILF internal logical files 7 / 10 / 15 EIF external interface files 5 / 7 / 10 Unadjusted FP = Σ (count × weight) Value adjustment factor VAF = 0.65 + (0.01 × TDI) TDI = sum of 14 general system characteristics, each rated 0–5 so VAF ranges 0.65 to 1.35 Adjusted FP = UFP × VAF Effort = adjusted FP × hours per FP (organisational productivity rate) Story points relative size, not time. Fibonacci scale 1,2,3,5,8,13. Effort = story points / velocity (L2). Never convert points to hours by a fixed ratio — that destroys their purpose.

Worked example — function points

ComponentLowAverageHighWeighted total
External inputs (EI)4 × 36 × 42 × 648
External outputs (EO)2 × 44 × 52 × 742
External inquiries (EQ)7 × 36 × 42 × 657
Internal logical files (ILF)1 × 73 × 102 × 1567
External interface files (EIF)1 × 52 × 71 × 1029
Unadjusted function points———243
EI = (4×3) + (6×4) + (2×6) = 12 + 24 + 12 = 48 UFP = 48 + 42 + 57 + 67 + 29 = 243 Total degree of influence: 14 characteristics, average rating 3 TDI = 14 × 3 = 42 VAF = 0.65 + (0.01 × 42) = 1.07 Adjusted FP = 243 × 1.07 = 260 Effort at an organisational rate of 8 hours per FP: 260 × 8 = 2,080 hours = 260 person-days At 1,400 per person-day = 364,000 — within 2% of the 370,900 bottom-up figure for WBS 1.2 (H1). Story points, same scope Backlog totals 340 story points. Team velocity 42 points per two-week sprint (L2). Sprints required = 340 / 42 = 8.1 → 9 sprints = 18 weeks Note this gives duration, not effort, and only for this team. A different team with a different velocity gets a different answer from the same 340 points — which is the point.
Exam trap. Function points measure delivered functionality and are comparable across teams and technologies. Story points measure relative effort for one specific team and are not comparable across teams. Using story points to compare two teams' productivity is the most common misuse, and it reliably destroys the estimates by incentivising inflation.

H4 Scope baseline variance and scope creep

Primary 4.5.3 Scope · KCI 4.5.3.4 Establish and maintain scope configuration Also 4.5.10 Plan and control

How much the scope has moved since baseline, how much of that movement was authorised, and what the unauthorised part is costing.

Two different quantities are routinely confused. Requirements volatility measures authorised churn — additions, changes and deletions that went through change control. Scope creep measures work delivered that never went through change control at all. Volatility is a planning-quality signal; creep is a control failure, and only creep is invisible to earned value.

Volatility (added + changed + deleted) / baseline count Scope creep unauthorised items delivered / baseline count Stability index 1 − (cumulative authorised churn / baseline count) Creep cost unauthorised items × average unit cost Authorised growth Σ approved change value / original BAC
Requirement population at month 4 baseline 240 +58 authorised +11 unauthorised (creep) never entered the baseline, so it consumes AC but generates no EV what earned value measures against stability index 0.758 1.0 = untouched baseline
Authorised change sits outside the baseline but inside the control system. Creep sits outside both, which is precisely why it does not appear as a scope variance.

Worked example

Baseline at approval: 240 requirements, BAC 500,000. Months 1–4, through change control: 34 added, 18 changed, 6 deleted. A scope audit finds a further 11 items built with no change request. Authorised churn 34 + 18 + 6 = 58 items Volatility 58 / 240 = 24.2% Stability index 1 − 0.242 = 0.758 Scope creep 11 / 240 = 4.6% Creep cost 11 × 1,900 = 20,900 unfunded 20,900 / 500,000 = 4.2% of BAC Effect on the indices The 20,900 lands in AC. None of it lands in EV, because none of it is in the performance measurement baseline. CPI falls with no identifiable cost overrun on any baselined package — the classic signature of creep rather than of poor productivity.
Exam trap. Deletions count towards volatility. They are churn, not a reduction in churn, because the analysis work was still spent — subtracting them flatters the figure. The bigger trap is diagnostic: a falling CPI with every baselined work package on budget does not mean the estimates were wrong, it means effort is going somewhere the baseline cannot see. A question that gives you healthy package-level performance and an unhealthy project-level CPI is asking you to name scope creep.

I  Requirements, objectives and benefits ICB4 4.5.2

I1 Benefits quantification

Primary 4.3.1 Strategy · KCI 4.3.1.3 Develop and ensure the ongoing validity of the business / organisational justification Also 4.5.2 Requirements and objectives

Turning a stated benefit into a number that can enter an appraisal.

Cashable benefit a cost that actually leaves the budget = unit cost × volume reduction Non-cashable benefit capacity released but not removed from the budget = hours saved × loaded rate (report separately) Avoided cost a future cost that will not now be incurred Revenue benefit = incremental volume × margin Risk-reduction benefit = EMV before − EMV after (from D2) Attribution benefit × attribution % where several initiatives contribute to the same outcome

Worked example

BenefitTypeCalculationAnnual value
Decommission legacy platformCashablelicences 148k + hosting 62k210,000
Reconciliation effort releasedNon-cashable3,200 h × 46147,200
Avoided regulatory remediationAvoided costEMV 0.15 × 400k60,000
Faster product onboardingRevenue6 products × 18k margin108,000
Total gross annual benefit——525,200
Attribution. The onboarding benefit is shared with a separate product-catalogue programme. Agreed attribution to this project: 40%. 108,000 × 0.40 = 43,200 (not 108,000) Cashability discipline. The finance director will only accept cashable and avoided-cost benefits in the business case: Cashable + avoided = 210,000 + 60,000 = 270,000 Attributed revenue = 43,200 Business-case annual benefit = 313,200 Non-cashable capacity release, reported separately = 147,200 Using the C1–C5 machinery on the cashable figure over five years: PV of benefits = 313,200 × 3.7908 = 1,187,278 Less five-year TCO from G4 (Beta) = 1,193,334 NPV = −6,056 — marginal on cashable benefits alone. Include the non-cashable release at even 30% realisation: 147,200 × 0.30 = 44,160 additional annual benefit PV = 44,160 × 3.7908 = 167,402 NPV = +161,346 The entire business case rests on whether released capacity is genuinely redeployed. State that dependency explicitly.
Exam trap. Time saved is not money saved unless the headcount is actually removed or redeployed to funded work. Twenty people each saving one hour a week is 0.5 FTE spread so thinly that no post is ever removed. Classify it as non-cashable, quantify it separately, and never let it carry an investment case on its own.

I2 KPI definition, baselining and target setting

Primary 4.3.1 Strategy · KCI 4.3.1.5 Determine, assess and review key performance indicators Also 4.5.2 Requirements and objectives

Making a benefit measurable before the project starts, so the claim can later be tested.

A complete KPI definition specifies the metric formula, the data source, the measurement frequency, the owner, the baseline value with its measurement date, the target value with its target date, and the tolerance Improvement = (current − baseline) / baseline Achievement vs target = (current − baseline) / (target − baseline) Index form = (current / baseline) × 100

Worked example

KPIBaselineTargetMonth 12ImprovementAchievement
Monthly reconciliation hours26780131−50.9%72.7%
Batch cycle time (min)18.412.012.4−34.8%93.8%
Production defect escapes / month1436−57.1%72.7%
Product onboarding lead time (days)451531−31.1%46.7%
Reconciliation hours: Improvement = (131 − 267) / 267 = −136 / 267 = −50.9% Achievement = (131 − 267) / (80 − 267) = −136 / −187 = 72.7% Batch cycle time: Improvement = (12.4 − 18.4) / 18.4 = −32.6% Achievement = (12.4 − 18.4) / (12.0 − 18.4) = −6.0 / −6.4 = 93.8% Why both figures are needed. Onboarding lead time shows a 31% improvement — presentable on its own. Against target it has achieved only 46.7%, less than half the intended change. Reporting improvement alone is the standard way benefits get overstated. Baseline integrity. The 267-hour baseline was measured over three months before go-live. If it had been measured in a single peak month (say 310 hours), the same month-12 result would show a 57.7% improvement rather than 50.9%. State the baseline period, or the percentage is unfalsifiable.
Exam trap. A KPI without a baseline measured before the intervention cannot demonstrate anything. Reconstructing a baseline afterwards from memory or from a convenient period is the commonest benefits-management failure, and assessors probe for it. The second probe: who owns the measurement after the project closes? A KPI with no post-closure owner will not be measured.

I3 Benefits realisation tracking

Primary 4.3.1 Strategy · KCI 4.3.1.3 Develop and ensure the ongoing validity of the business / organisational justification Also 4.5.10 Plan and control

Comparing benefits actually delivered against the profile forecast in the business case.

Realisation rate = actual benefit / forecast benefit for the period Cumulative gap = Σ forecast − Σ actual to date Revised NPV recompute the appraisal on the actual profile Benefit lag the delay between capability delivery and benefit flow — must be in the forecast profile, not assumed away Realisation ratio at close = PV of actual benefits / PV of forecast

Worked example

PeriodForecastActualRateCumulative forecastCumulative actual
Yr 1 H178,30000%78,3000
Yr 1 H278,30044,00056%156,60044,000
Yr 2 H1156,600121,00077%313,200165,000
Yr 2 H2156,600148,00095%469,800313,000
To date469,800313,00066.6%—gap 156,800
Run-rate is fine; the profile was wrong. Latest period realisation = 148,000 / 156,600 = 94.5% Cumulative realisation = 313,000 / 469,800 = 66.6% The steady state is nearly on plan. The cumulative shortfall of 156,800 came almost entirely from year 1, where the business case assumed benefits began flowing at go-live and they in fact took twelve months to ramp. Benefit lag. Actual ramp: 0%, 56%, 77%, 95%. The forecast assumed 100% from period 1. A realistic lag profile (0%, 50%, 80%, 100%) would have cut forecast year-1 benefits by 117,450 and the business case would still have passed — but the project would not now be carrying a 157k "shortfall" it never actually caused. Revised NPV on the actual profile, assuming 313,200 steady state from year 3 at 10%: Yr1 44,000 × 0.9091 = 40,000 Yr2 269,000 × 0.8264 = 222,302 Yr3 313,200 × 0.7513 = 235,307 Yr4 313,200 × 0.6830 = 213,916 Yr5 313,200 × 0.6209 = 194,466 PV of benefits = 905,991 against a forecast PV of 1,187,278 Realisation ratio = 905,991 / 1,187,278 = 76.3%
Exam trap. Benefits are realised after the project closes, so the project manager is accountable for delivering the capability and for handing over a measurable benefits profile with a named owner — not for the benefits themselves. A question asking who is accountable for benefits realisation wants the business change owner or sponsor, not the project manager.

J  Organisation, information and stakeholders ICB4 4.5.5 / 4.5.12

J1 Communication channels

Primary 4.5.5 Organisation and information · KCI 4.5.5.3 Establish infrastructure, processes and systems for information flow Also 4.5.12 Stakeholders

Why coordination cost grows faster than team size.

Channels = n(n − 1) / 2 n = number of people Change when adding people Δ = nnew(nnew−1)/2 − nold(nold−1)/2 With a hub structure channels = n − 1 (everyone through one point) Sub-team structure Σ within-team channels + between-team channels

Worked example

n = 6: 6 × 5 / 2 = 15 channels n = 10: 10 × 9 / 2 = 45 channels n = 15: 15 × 14 / 2 = 105 channels Adding four people to a team of six Δ = 45 − 15 = +30 channels Team size rose 67%; coordination surface rose 200%. This is why F3's warning holds: the marginal engineer adds less than the last one. Structural alternatives at n = 15 Fully connected = 105 channels Hub (all through the PM) = 15 − 1 = 14 channels but the PM becomes the bottleneck Three sub-teams of 5, with one liaison each: within teams 3 × (5 × 4 / 2) = 3 × 10 = 30 between liaisons 3 × 2 / 2 = 3 total = 33 channels A 69% reduction against full connection, without a single bottleneck. Including stakeholders Core team 15 + steering group 6 + vendor 4 = 25 people 25 × 24 / 2 = 300 channels if unmanaged. This is the arithmetic case for a communications plan.
Exam trap. The formula counts possible channels, not channels in use. Its value is comparative — showing how fast the coordination surface grows and justifying structure. Quoting 300 channels as though 300 conversations occur is a misreading; the correct use is "unmanaged, this configuration has 300 potential channels, so we are structuring it as follows".

J2 Power-interest grid scoring

Primary 4.5.12 Stakeholders · KCI 4.5.12.1 Identify stakeholders and analyse their interests and influence Also 4.3.4 Power and interest

Sorting stakeholders into engagement strategies using two scored dimensions.

Score each stakeholder power 1–5, interest 1–5 Quadrant high power / high interest → manage closely high power / low interest → keep satisfied low power / high interest → keep informed low power / low interest → monitor Engagement gap = desired engagement level − current level (unaware / resistant / neutral / supportive / leading)
keep satisfied manage closely monitor keep informed S1 S2 S3 S4 S5 interest → power → 15
Position sets the strategy; the engagement gap sets the effort.

Worked example

StakeholderPowerInterestScoreQuadrantCurrentDesiredGap
S1 Group CRO5420Manage closelyNeutral (3)Supportive (4)1
S2 Head of Operations4312Manage closelyResistant (2)Leading (5)3
S3 External auditor428Keep satisfiedNeutral (3)Neutral (3)0
S4 Reconciliation team lead2510Keep informedSupportive (4)Leading (5)1
S5 Facilities212MonitorUnaware (1)Unaware (1)0
Where the effort goes. Raw score ranks S1 highest (20). Engagement gap ranks S2 highest (3). S1 needs one step of movement and already sits at neutral; S2 needs three steps and is actively resistant while holding power 4. Effort priority = power × gap S1: 5 × 1 = 5 S2: 4 × 3 = 12 ← the real priority S4: 2 × 1 = 2 S3, S5: 0 S2 is the stakeholder who can stop this project, is currently against it, and is not the highest-scoring name on the grid. Position alone would have missed that.
Exam trap. The grid is a snapshot and stakeholders move — particularly interest, which rises sharply as go-live approaches. A stakeholder in "monitor" during design routinely becomes "manage closely" during cutover. Re-score at each phase gate. Also: never write the grid into a document a stakeholder might read.

J3 Stakeholder salience

Primary 4.5.12 Stakeholders · KCI 4.5.12.1 Identify stakeholders and analyse their interests and influence Also 4.3.4 Power and interest

A three-attribute model that resolves cases the two-dimensional grid handles badly.

Three attributes Power the ability to impose their will Legitimacy a recognised right to make the claim Urgency the claim is time-sensitive and important to them Seven classes One attribute — latent Dormant power only Discretionary legitimacy only Demanding urgency only Two attributes — expectant Dominant power + legitimacy Dangerous power + urgency Dependent legitimacy + urgency Three — Definitive: power + legitimacy + urgency Salience score = number of attributes held (0–3), optionally weighted

Worked example

StakeholderPowerLegitimacyUrgencyClassResponse
Group CRO✓✓✓DefinitiveImmediate priority
Head of Operations✓✓—DominantFormal engagement, board seat
Regulator✓✓—DominantFormal, scheduled
Reconciliation team—✓✓DependentNeeds an advocate — find them one
Legacy vendor✓—✓DangerousMonitor closely; can disrupt
Facilities✓——DormantMonitor; could acquire urgency
What salience catches that the grid misses. 1. Dependent stakeholders — the reconciliation team has a legitimate, urgent claim and no power. The power-interest grid files them under "keep informed" and they get ignored. Salience says their claim is valid and they need a powerful advocate, which is an action, not a communication frequency. 2. Dangerous stakeholders — the legacy vendor has power and urgency but no legitimate claim on the project's direction. They will act, and their action will not be through governance channels. The grid would place them high on power and moderate on interest, implying "keep satisfied", which is the wrong instinct. 3. Dormant stakeholders — facilities have power (site access at cutover) but neither legitimacy nor urgency today. Attributes are transient: give them urgency by scheduling a weekend cutover and they become Dangerous overnight. Salience is dynamic. Re-assess when the project acquires urgency, because urgency is the attribute that moves fastest.
Exam trap. Attributes are binary and, crucially, they are perceived rather than objective — a stakeholder is legitimate if management perceives the claim as legitimate. That perception can be wrong, and correcting it is itself a stakeholder-management action. Expect questions where a Dependent stakeholder's claim is dismissed and the project later fails because of it.

J4 RACI completeness checks

Primary 4.5.5 Organisation and information · KCI 4.5.5.2 Define the structure, roles and responsibilities within the project

Testing a responsibility matrix for the structural faults that cause work to fall through.

R Responsible does the work — can be several per activity A Accountable answers for the outcome — exactly one per activity C Consulted two-way, before the decision I Informed one-way, after the decision Row checks exactly one A; at least one R; not too many C Column checks no person with A on everything (bottleneck); no person with only I (why are they on the chart); no person with R on everything (overload) Load count R + A per person against their available capacity (F3)

Worked example

ActivityPMSponsorData leadTest leadOpsRow check
Approve mapping rulesCARCIOK
Execute migration runAIRCROK
Sign off test exitCACRCOK
Authorise cutoverRACCATwo A's — fail
Post-cutover reconciliationIICCINo R, no A — fail
Decommission legacyAICIROK
Row failures Authorise cutover: two Accountables. In a real cutover this resolves itself at 03:00 as a standoff. One A — here the sponsor; Ops becomes R. Post-cutover reconciliation: nobody Responsible and nobody Accountable. Four people are Consulted or Informed about work that no one is doing. This is the fault that most often survives review, because the row looks populated. Column analysis PM Sponsor Data Test Ops A count 2 3 0 0 1 R count 1 0 2 1 2 C count 2 0 3 4 1 I count 1 3 0 1 2 Sponsor holds A on 3 of 6 — appropriate for decision gates. Test lead has C on 4 of 6 and R on 1. Heavy consultation load with little ownership: either they should be R somewhere, or several C's should be downgraded to I. Data lead: R on 2, C on 3. Reasonable. Load check against capacity (F3) Data lead R on two activities totalling 62 person-days over 4 months. Available: 15.2 days/month × 4 = 60.8 days at 100% allocation. 62 > 60.8 — over-committed before any contingency.
Exam trap. Exactly one A per row is the rule most often broken, and shared accountability is the same as no accountability. The second-most-common fault is C inflation: every C is a two-way conversation that must complete before the decision, so a row with five C's is a decision that will not be made this week. If a question shows a RACI with heavy consultation, the expected observation is decision latency.

K  Design and selection ICB4 4.5.1

K1 Weighted scoring model for option selection

Primary 4.5.1 Project design · KCI 4.5.1.4 Select and review the overall project management approach

Choosing between delivery approaches when the criteria are measured in different units.

The mechanics match supplier scoring (G3), but the hard part here is normalising criteria that arrive in euros, months, headcount and judgement onto one comparable scale before weighting.

Normalisation — higher is better score = (value / best value) × 10 Normalisation — lower is better score = (best value / value) × 10 Min-max normalisation score = (value − min) / (max − min) × 10 Weighted total = Σ (weight × normalised score) Robustness test re-run with weights shifted ±10 points and see whether the ranking survives

Worked example — three delivery approaches

CriterionWeightBig bangPhased by productParallel run
Cost (raw)—730,000812,000965,000
Duration (raw)—12 mo17 mo15 mo
Cutover risk (1–10, 10 best)—389
Business disruption (10 best)—476
Normalise Cost, lower is better: 730/730 × 10 = 10.0 730/812 × 10 = 9.0 730/965 × 10 = 7.6 Duration, lower is better: 12/12 × 10 = 10.0 12/17 × 10 = 7.1 12/15 × 10 = 8.0 Risk and disruption already on a 1–10 scale.
CriterionWeightBig bangPhasedParallelBB wtdPh wtdPa wtd
Cost0.2510.09.07.62.502.251.90
Duration0.1510.07.18.01.501.071.20
Cutover risk0.353891.052.803.15
Business disruption0.254761.001.751.50
Total1.00———6.057.877.75
Result Phased 7.87 > Parallel 7.75 > Big bang 6.05 Robustness test. Shift 10 points of weight from cutover risk (0.35 → 0.25) to cost (0.25 → 0.35): Big bang = 3.50 + 1.50 + 0.75 + 1.00 = 6.75 Phased = 3.15 + 1.07 + 2.00 + 1.75 = 7.97 Parallel = 2.66 + 1.20 + 2.25 + 1.50 = 7.61 Phased still leads and its margin widens. The recommendation is robust. The margin between Phased and Parallel is 0.12 on a 10-point scale — 1.5%. Report those two as effectively tied and let a qualitative factor break it, rather than presenting a false precision.
Exam trap. Direction of normalisation. Cost and duration are "lower is better" and must be inverted before scoring; risk and satisfaction scales are usually "higher is better". Mixing the directions inside one model silently ranks the worst option first, and the total still looks plausible.

K2 Analytic hierarchy process and pairwise comparison

Primary 4.5.1 Project design · KCI 4.5.1.4 Select and review the overall project management approach Also 4.5.2 Requirements and objectives

Deriving criterion weights from a series of two-way comparisons instead of asking people to assign percentages directly, and testing whether their judgements were coherent.

Saaty scale 1 equal, 3 moderately more important, 5 strongly, 7 very strongly, 9 extremely; reciprocals for the inverse Priority vector normalise each column (divide by its sum), then average across each row Consistency λmax = mean of (row of A×w) / wi CI = (λmax − n) / (n − 1) CR = CI / RI RI: n=3 → 0.58 n=4 → 0.90 n=5 → 1.12 n=6 → 1.24 n=7 → 1.32 Accept if CR < 0.10 otherwise revisit the judgements

Worked example

Three criteria compared pairwise: cost, technical fit, regulatory compliance.

 CostTechnicalRegulatory
Cost11/21/3
Technical211/2
Regulatory321
Column sum6.00003.50001.8333
Step 1 — normalise each column, average each row Cost Tech Reg row average Cost 1/6=.1667 .5/3.5=.1429 .3333/1.8333=.1818 0.1638 Tech 2/6=.3333 1/3.5=.2857 .5/1.8333=.2727 0.2972 Reg 3/6=.5000 2/3.5=.5714 1/1.8333=.5455 0.5390 sum 1.0000 ✓ Step 2 — consistency compute A×w row by row Row 1: 1(.1638) + 0.5(.2972) + 0.3333(.5390) = 0.4921 λ₁ = 0.4921 / 0.1638 = 3.004 Row 2: 2(.1638) + 1(.2972) + 0.5(.5390) = 0.8943 λ₂ = 0.8943 / 0.2972 = 3.009 Row 3: 3(.1638) + 2(.2972) + 1(.5390) = 1.6248 λ₃ = 1.6248 / 0.5390 = 3.014 λ_max = (3.004 + 3.009 + 3.014) / 3 = 3.009 CI = (3.009 − 3) / (3 − 1) = 0.009 / 2 = 0.0045 CR = 0.0045 / 0.58 = 0.008 → 0.8%, well below 10% ✓ Resulting weights cost 16.4%, technical 29.7%, regulatory 53.9% What an inconsistent judgement looks like. If the assessor had also said cost is more important than regulatory (a 3 in the Cost/Reg cell instead of 1/3), the matrix would assert Reg > Tech > Cost > Reg — a cycle. CR would rise well above 0.10 and the judgements would have to be revisited rather than averaged into a meaningless weight.
Exam trap. The matrix must be reciprocal: if cell (i,j) is 3, cell (j,i) must be 1/3, and the diagonal must be all 1s. AHP's real contribution is the consistency ratio — it is the only method in this document that tests whether the human judgements feeding the model were coherent. Quoting AHP weights without a CR is quoting half the method.

K3 Complexity scoring

Primary 4.5.1 Project design · KCI 4.5.1.3 Determine complexity and its consequences for the approach

Rating a project's management complexity against a defined indicator set — the basis for IPMA certification-level eligibility and for internal governance tiering.

IPMA's competence baseline treats complexity as the discriminator between certification levels, and certification bodies operationalise it as a scored indicator model. The indicators come from ICB4; the number of points and the pass thresholds are set by each certification body, so confirm your CB's published figures before relying on any specific number.

Typical model ~10 complexity indicators, each scored 0–4, giving a maximum around 40 Indicator families objectives and assessment processes, methods, tools organisation and structure resources and skills interfaces and dependencies time, cost and finance stakeholder and political change and innovation degree autonomy and leadership scope cultural and social context Use score each qualifying project; compare the total against the threshold for the level applied for Thresholds are CB-specific — commonly around 16/40 for Level C and 25/40 for Level B in the Project domain

Worked example

IndicatorScore 0–4Evidence anchor
Objectives and assessment3Multiple conflicting success criteria across three business units
Interfaces and dependencies4Nine upstream systems, two external vendors, one regulator
Cultural and social context2Two countries, one language boundary
Organisation and structure3Matrix, no direct line authority over 11 of 15 staff
Processes, methods and tools3Hybrid delivery; new toolchain introduced mid-project
Resources and skills2Two scarce skill sets, both single-point
Time, cost and finance3Regulatory deadline, multi-currency, capitalisation rules
Stakeholder and political4Board-level sponsor conflict, external regulatory scrutiny
Degree of innovation2Established technology, novel to this organisation
Autonomy and leadership3Full delegated authority within an approved budget
Total29 / 40—
Total = 3+4+2+3+3+2+3+4+2+3 = 29 of a possible 40 Against a 25/40 Level B threshold: qualifies, with 4 points of margin. Where the margin is fragile. Two indicators carry a 4. If an assessor marks stakeholder complexity at 3 rather than 4 — a defensible reading — the total falls to 28, still clear. Two such adjustments give 27. The project survives normal assessor variation. A project scoring 25 or 26 does not. For a portfolio of qualifying projects, target a comfortable margin on each rather than a bare pass, because the score is a judgement and judgements vary. Evidence discipline. Each score needs a specific, checkable anchor. "Complex stakeholder environment: 4" is not evidence. "Board-level sponsor conflict escalated twice to the group risk committee, plus direct regulatory correspondence: 4" is.
Exam trap. Complexity is not size. A large, repetitive, single-stakeholder rollout with a well-understood technology can be a €20m project with a low complexity score, while a €900k regulatory remediation with nine interfaces and a hostile board scores high. Arguing complexity from budget or headcount alone is the most common weakness in certification applications.

K4 Portfolio prioritisation under constraint

Primary 4.3.1 Strategy Also 4.5.1 Project design

Choosing the set of projects that maximises value when the budget, or a scarce skill, will not fund everything.

Unconstrained accept every project with NPV > 0 Capital rationing maximise total NPV subject to Σ investment ≤ budget divisible projects → rank by profitability index (C5), fill the budget indivisible projects → evaluate feasible combinations; PI ranking can leave budget stranded and miss the optimum Multiple constraints budget and a scarce resource → check both Must-do projects regulatory and mandatory work is committed before optimisation; optimise the remainder

Worked example

Budget €1,000,000. Five candidate projects. Project R is a regulatory obligation.

ProjectInvestmentNPVPIScarce data engineersStatus
R Regulatory reporting300,000−40,0000.872Mandatory
W Migration400,00054,8961.1373Candidate
X Reporting platform200,00038,0001.1902Candidate
Y Channel refresh500,00061,0001.1221Candidate
Z Automation pilot120,00019,0001.1583Candidate
Step 1 — commit the mandatory project. R is negative-NPV but not optional. Budget remaining = 1,000,000 − 300,000 = 700,000. Data engineers remaining = 6 − 2 = 4. Step 2 — rank the rest by PI X 1.190 > Z 1.158 > W 1.137 > Y 1.122 Step 3 — PI-greedy fill X 200,000 (2 eng) → remaining 500,000, 2 engineers Z 120,000 (3 eng) → blocked: only 2 engineers left W 400,000 (3 eng) → blocked on engineers Y 500,000 (1 eng) → fits Selection: X + Y. Cost 700,000, engineers 3. Total NPV = 38,000 + 61,000 = 99,000 Step 4 — test the feasible combinations (indivisible projects) X + Y 700,000 3 eng NPV 99,000 ✓ feasible W + X 600,000 5 eng — exceeds 4 engineers W + Z 520,000 6 eng — exceeds 4 engineers X + Z 320,000 5 eng — exceeds 4 engineers Y + Z 620,000 4 eng NPV 80,000 ✓ feasible W alone 400,000 3 eng NPV 54,896 ✓ feasible Y alone 500,000 1 eng NPV 61,000 ✓ feasible Optimum: X + Y, NPV 99,000. Here the PI-greedy answer happens to be optimal, but only because Y's low engineer demand rescued it — Z was rejected purely on the resource constraint, not the budget. The lesson. With two binding constraints, PI ranking is a starting heuristic, not the answer. You must enumerate feasible combinations. Note also that 300,000 of the budget produced −40,000 of NPV: the portfolio's economic return is 59,000 on 1,000,000, or 5.9%, and that is the honest headline figure.
Exam trap. Two habits earn marks here. First, deal with mandatory work before optimising — a regulatory project with negative NPV is not a candidate for rejection, it is a constraint. Second, identify which constraint binds. In this example the budget was not the binding constraint at all; scarce data engineers were, and a question that only mentions money is often hiding a resource limit in the project descriptions.

L  Agile and hybrid delivery

L1 Story points and relative estimating

Cross-cutting no single primary element Supports 4.5.4 Time · 4.5.3 Scope

Sizing work by comparison rather than by predicted duration, so that estimates stay stable while team speed changes.

Principle a story point expresses size relative to a reference story, combining volume, complexity and uncertainty. It is not a unit of time. Scale modified Fibonacci 1, 2, 3, 5, 8, 13, 20, 40, 100 the widening gaps encode falling precision at larger sizes Planning poker simultaneous reveal, discuss the outliers, re-vote Anchoring pick one well-understood story as the 3 or 5 and size everything against it Splitting rule anything above 13 is split before it enters a sprint

Worked example

Reference story: "migrate a simple lookup table with validation" = 3 points Migrate a second simple lookup table about the same 3 Migrate a complex table, 40 columns, 3 joins ~2× the work 8 Migrate reference data with manual mapping bigger and unclear 13 Add a progress indicator to the run screen much smaller 1 Build the reconciliation engine far too big 40 → split Splitting the 40: reconciliation rules engine 13 variance report 8 exception queue 8 automated re-run trigger 5 total after splitting 34 The split total is lower than the unsplit estimate. That is normal and informative: the 40 encoded uncertainty that decomposition removed. Why not just estimate in days? Team A: 8 points takes 3 days. Team B: 8 points takes 5 days. Both are correct. The story is the same size; the teams differ. Points stay stable when the team changes, when someone is on leave, and when a new tool speeds the work up — velocity absorbs all of that (L2), and the backlog estimate does not have to be redone.
Exam trap. The moment a fixed conversion is published — "one point equals one day" — story points become hours with extra steps, and the team will inflate them under schedule pressure. Points are converted to time only through observed velocity, which is measured, not decreed. Any question proposing a points-to-hours ratio is testing this.

L2 Velocity and capacity planning

Cross-cutting no single primary element Supports 4.5.4 Time · 4.5.8 Resources

Forecasting how much a team will complete, from what it has actually completed.

Velocity = story points completed per sprint (only fully done items) Average velocity = mean of the last 3–6 sprints Sprints remaining = remaining backlog points / average velocity Forecast range use the min and max observed velocity, not the mean alone Capacity-adjusted velocity = average velocity × (available person-days this sprint / normal available person-days)

Worked example

Sprint123456
Points completed384541444240
Average velocity = (38+45+41+44+42+40) / 6 = 250 / 6 = 41.7 points Min 38, max 45, standard deviation 2.58 (see M1) Release forecast remaining backlog 340 points Optimistic 340 / 45 = 7.6 → 8 sprints Expected 340 / 41.7 = 8.2 → 9 sprints Pessimistic 340 / 38 = 8.9 → 9 sprints At 2-week sprints: 16 to 18 weeks. Quote the range, not "8.2 sprints". Capacity adjustment for sprint 7 Normal capacity: 5 people × 10 days = 50 person-days Sprint 7: one person on leave 5 days, one at 50% on an incident = 50 − 5 − 5 = 40 person-days Adjusted velocity = 41.7 × (40 / 50) = 33.4 points Committing 42 points to sprint 7 would over-commit by 26%. Effect on the release forecast If sprint 7 delivers 33 instead of 42, remaining after sprint 7 = 340 − 33 = 307, 307 / 41.7 = 7.4 → 8 more sprints. Total 9 sprints, unchanged — the buffer in rounding absorbed it.
Exam trap. Velocity counts only items meeting the definition of done. Partial credit for unfinished stories destroys the metric's forecasting value, because the points get counted twice across two sprints. Second point: velocity is a forecasting input, never a performance target. The moment it is used to compare teams or set goals, it is inflated and stops forecasting anything.

L3 Burndown, burnup and release forecasting

Cross-cutting no single primary element Supports 4.5.10 Plan and control · 4.5.4 Time

Tracking remaining work against time, and separating genuine progress from scope growth.

Burndown plots remaining work falling toward zero ideal line = total work × (1 − elapsed / total duration) weakness: scope added and work completed both move the same line, so they cancel and become invisible Burnup plots completed work rising, with a separate scope line scope growth is visible as the upper line rising forecast completion = where the two trend lines converge Forecast remaining work / current completion rate
total scope — rising original plan line completed forecast finish sprint 9 10.7 sprint story points
The burnup separates the two signals: the team's rate is on plan, and the finish date has moved because scope grew by 12%.

Worked example

Release scope at sprint 0: 340 points. Plan: 9 sprints at 41.7. Actual scope by sprint: 340, 340, 340, 356, 356, 356, 380, 380, 380 Completed cumulative: 42, 84, 126, 168, 210, 251, 293, 335, 377 At end of sprint 6 Completed 251 of 380 = 66% Burndown reading: remaining = 380 − 251 = 129 points Original remaining at this point should have been 340 − 250 = 90. The burndown line looks 39 points behind and gives no reason why. Burnup reading Completion rate = 251 / 6 = 41.8 points per sprint — exactly on plan Scope growth = 380 − 340 = 40 points, +11.8% The team is performing to plan; the scope grew. Forecast Remaining = 380 − 251 = 129 Sprints needed = 129 / 41.8 = 3.1 → finish in sprint 9.1 If scope continues growing at 6.7 points per sprint: convergence where 251 + 41.8s = 380 + 6.7s 35.1s = 129 s = 3.7 → finish at sprint 9.7, call it 10 Two-thirds of a sprint of the delay comes from future scope growth, which is a change-control problem, not a delivery problem.
Exam trap. A flat burndown is ambiguous by construction: it means either that nothing was completed, or that exactly as much scope was added as was completed. The two situations demand opposite responses. Whenever a question presents a burndown that is not falling, the expected answer is that a burnup is needed to tell which case applies.

L4 Cycle time, throughput and Little's Law

Cross-cutting no single primary element Supports 4.5.4 Time · 4.5.10 Plan and control

The relationship between how much work is in progress, how fast it flows, and how long each item takes.

Little's Law WIP = throughput × cycle time rearranged: cycle time = WIP / throughput Lead time from customer request to delivery (includes waiting) Cycle time from work starting to delivery (excludes the queue) Throughput items completed per unit time Flow efficiency = active work time / total lead time typically 5–15% in unoptimised knowledge work Queueing effect of utilisation queue multiplier ≈ ρ / (1 − ρ) ρ = utilisation ρ = 0.70 → 2.3 0.80 → 4.0 0.90 → 9.0 0.95 → 19.0

Worked example

Current state Items in progress (WIP) = 24 Throughput = 6 items per week Cycle time = WIP / throughput = 24 / 6 = 4.0 weeks Halve the WIP, change nothing else WIP = 12, throughput unchanged at 6 Cycle time = 12 / 6 = 2.0 weeks Same throughput, half the cycle time. Items are delivered twice as fast without anyone working faster — they simply stop waiting. In practice throughput usually rises too, because less context switching. If throughput rises to 7: Cycle time = 12 / 7 = 1.7 weeks Lead time and flow efficiency Lead time = 6.5 weeks (2.5 weeks queueing before work starts) Cycle time = 4.0 weeks Active hands-on time within the cycle = 0.8 weeks Flow efficiency = 0.8 / 6.5 = 12.3% Nearly 88% of elapsed time is waiting. Optimising the 12% — making people work faster — addresses the smaller share by a wide margin. Utilisation and queues (connects to F3) At 70% utilisation, queue multiplier = 0.70 / 0.30 = 2.3 At 90% utilisation, queue multiplier = 0.90 / 0.10 = 9.0 Raising a team from 70% to 90% utilised increases queueing delay fourfold. Full utilisation of a variable process guarantees queues; this is the quantitative case against 100%-loaded resource plans.
Exam trap. Little's Law needs a stable system to hold — arrivals roughly equal to departures over the measurement window, and consistent definitions of what counts as WIP. Applied to a system where work is piling up, it understates cycle time. Second trap: lead time and cycle time are different quantities and the customer experiences lead time. Reporting a healthy cycle time while the queue grows is technically true and practically misleading.

L5 Cumulative flow diagram and WIP limits

Cross-cutting no single primary element Supports 4.5.10 Plan and control · 4.5.4 Time

Seeing where work accumulates, and capping it so the queue cannot grow.

A CFD stacks cumulative item counts by workflow state over time. The vertical thickness of a band is the WIP in that state; the horizontal distance between the top and bottom lines at a given height is the approximate lead time.

Band thickness = WIP in that state at that time Horizontal distance = approximate lead time Widening band = a bottleneck; arrivals exceed departures Flat top line = nothing being delivered Parallel bands = stable, healthy flow WIP limit a hard cap per state. When the cap is reached, no new work is pulled in — the team helps clear the constrained state. Starting point: roughly 1–1.5 items per person in the state.
done in progress testing — band widening backlog WIP 14 lead time time cumulative items
The testing band widens across the period while the others hold steady — the bottleneck is testing, not development.

Worked example

Reading the diagram In progress band, week 1: 6 items week 8: 7 items stable Testing band, week 1: 4 items week 8: 14 items growing Done line slope: 6 items per week unchanged Development is producing at 6 per week; testing is clearing fewer. WIP in testing grew by 10 items over 8 weeks, so testing throughput is 6 − (10 / 8) = 4.75 items per week. Cycle time impact via Little's Law (L4) Testing cycle time, week 1: 4 / 4.75 = 0.8 weeks Testing cycle time, week 8: 14 / 4.75 = 2.9 weeks Total lead time has grown by 2.1 weeks with no change in effort. Setting WIP limits Team: 4 developers, 2 testers. In progress limit = 4 × 1.5 = 6 Testing limit = 2 × 1.5 = 3 With a testing limit of 3, the system would have stopped pulling new development work at week 2, and the developers would have moved to testing. Throughput would have equalised at roughly 4.75–5.5 per week instead of accumulating a 14-item queue. The counter-intuitive result. Capping WIP lowers apparent developer utilisation and raises delivered throughput, because the constraint sets the system's rate. Anything the non-constraint produces beyond the constraint's capacity becomes inventory, not output.
Exam trap. A widening band identifies where work accumulates, which is downstream of nothing — it is the constraint. The instinct to add capacity to the busiest-looking upstream state makes the queue worse. Second point: a CFD with a flat "done" line and healthy-looking activity elsewhere means the system is producing inventory, not value.

M  Underlying statistics

M1 Central tendency and dispersion

Cross-cutting no single primary element Supports 4.5.11 Risk and opportunity · 4.5.6 Quality

The four numbers that summarise any dataset, and when each one misleads.

Mean x̄ = Σx / n sensitive to outliers Median middle value when sorted robust to outliers Mode most frequent value useful for categories Range max − min Population variance σ² = Σ(x − μ)² / N Sample variance s² = Σ(x − x̄)² / (n − 1) note n − 1 Standard deviation the square root of the variance Coefficient of variation CV = s / x̄ comparable across scales

Worked example

Sprint velocities from L2: 38, 45, 41, 44, 42, 40.

Sorted: 38, 40, 41, 42, 44, 45 Mean = 250 / 6 = 41.67 Median = (41 + 42) / 2 = 41.5 Mode = none; every value appears once Range = 45 − 38 = 7 Deviations and squares x x − x̄ (x − x̄)² 38 −3.67 13.47 45 3.33 11.09 41 −0.67 0.45 44 2.33 5.43 42 0.33 0.11 40 −1.67 2.79 Σ = 33.34 Sample variance s² = 33.34 / (6 − 1) = 33.34 / 5 = 6.67 Sample std dev s = √6.67 = 2.58 Population variance σ² = 33.34 / 6 = 5.56, σ = 2.36 Coefficient of variation = 2.58 / 41.67 = 6.2% Why CV matters. A second team averages 12.4 points with s = 1.9. Raw comparison: team 1 is more variable (2.58 > 1.9). CV comparison: team 1 = 6.2%, team 2 = 1.9/12.4 = 15.3% Team 2 is two and a half times more variable relative to its own output, and therefore the harder team to forecast. Where the mean misleads. Add one sprint of 12 points (a holiday sprint): Mean falls to 250+12 = 262/7 = 37.4 Median falls only to 41 The mean now forecasts a release date the team will beat, on the strength of one atypical sprint. Use the median, or exclude known-atypical periods and say that you did.
Exam trap. The n−1 denominator applies when the data is a sample used to estimate a wider population; n applies when the data is the whole population. Six observed sprints used to forecast future sprints is a sample → n−1. Six sprints being described as a completed release is a population → n. The difference here is 6.67 against 5.56, roughly 20% in variance.

M2 Normal distribution, z-scores and confidence intervals

Cross-cutting no single primary element Supports 4.5.11 Risk and opportunity · 4.5.6 Quality

Attaching a probability to a value, and a range to an estimate.

Z-score z = (x − μ) / σ how many standard deviations from the mean Empirical rule ±1σ ≈ 68.3% ±2σ ≈ 95.4% ±3σ ≈ 99.7% One-tailed z values 80% 0.842 90% 1.282 95% 1.645 99% 2.326 Two-tailed z values 90% 1.645 95% 1.960 99% 2.576 Confidence interval for a mean CI = x̄ ± z × (s / √n) s / √n is the standard error use the t-distribution when n < 30 and σ is unknown
μ −1σ+1σ −2σ+2σ 68.3% 95.4% 99.7% used in PERT (A3),SPC limits (E2),capability (E3),sampling (E4)
The 3σ band is why SPC control limits sit where they do: outside them, chance alone explains 0.3% of points.

Worked example

Z-score batch processing time μ = 12.0 min, σ = 0.6 min. A batch took 13.5 minutes. z = (13.5 − 12.0) / 0.6 = 1.5 / 0.6 = +2.50 P(Z > 2.50) = 0.0062 → 0.62% of batches exceed this by chance. Within 3σ control limits, so not an SPC signal — but worth watching. Confidence interval for velocity x̄ = 41.67, s = 2.58, n = 6 Standard error = 2.58 / √6 = 2.58 / 2.449 = 1.053 95% CI (using z = 1.96) = 41.67 ± (1.96 × 1.053) = 41.67 ± 2.06 = 39.6 to 43.7 points With n = 6 the t-distribution is more appropriate: t(0.025, 5) = 2.571 CI = 41.67 ± (2.571 × 1.053) = 41.67 ± 2.71 = 39.0 to 44.4 The small sample widens the interval by 31%. Applying it to the release forecast 340 points remaining: at the CI lower bound 39.0 → 8.7 → 9 sprints at the CI upper bound 44.4 → 7.7 → 8 sprints So "8 to 9 sprints, 95% confidence" — a defensible statement, unlike the point estimate of 8.2. Confidence and sample size Standard error falls with √n, so halving it requires quadrupling n. With 24 sprints of data: SE = 2.58 / √24 = 0.527, CI = ±1.03.
Exam trap. One-tailed and two-tailed z-values differ and get swapped constantly. "90% confidence of finishing on or before a date" is one-tailed → z = 1.282. "A 90% confidence interval around the mean" is two-tailed → z = 1.645. Using 1.645 where 1.282 belongs overstates the required buffer by 28%.

M3 Weighted averages, percentages, ratios and index numbers

Cross-cutting no single primary element Supports 4.5.10 Plan and control · 4.5.7 Finance

The arithmetic that carries most of the marks in a calculation paper, and most of the errors.

Weighted average = Σ(wixi) / Σwi Percentage change = (new − old) / old × 100 Percentage point an absolute difference between two percentages — not the same as a percentage change Reverse a percentage original = final / (1 + rate) Compound change final = original × (1 + r1)(1 + r2)… Index number = (current value / base value) × 100 Deflating with an index real value = nominal × (base index / current index)

Worked example

Weighted average day rate Senior 4 people at 1,850 Mid 7 people at 1,400 Junior 4 people at 950 Simple average of the rates = (1,850 + 1,400 + 950) / 3 = 1,400 Weighted average = [(4×1,850) + (7×1,400) + (4×950)] / 15 = (7,400 + 9,800 + 3,800) / 15 = 21,000 / 15 = 1,400 Coincidentally equal here. Change the mix to 2 senior, 4 mid, 9 junior: simple average unchanged at 1,400 weighted = (3,700 + 5,600 + 8,550) / 15 = 17,850 / 15 = 1,190 A 15% difference on the same three rates. Always weight by headcount. Percentage vs percentage point CPI moved from 0.95 to 0.871. Percentage-point change = 0.871 − 0.95 = −0.079, or 7.9 points Percentage change = −0.079 / 0.95 = −8.3% Both are correct statements of the same movement, and they are different numbers. State which one you mean. Reversing a percentage A quote of 806,000 includes 24% VAT. The net amount is not 806,000 × 0.76 = 612,560. net = 806,000 / 1.24 = 650,000 VAT = 806,000 − 650,000 = 156,000 check: 650,000 × 1.24 = 806,000 ✓ Compounding Costs rose 8% in year 1 and fell 8% in year 2. Net change = 1.08 × 0.92 = 0.9936 → −0.64%, not zero. Index numbers Construction cost index: 2022 = 100, 2024 = 118, 2026 = 131. A 2022 contract of 450,000 escalated to 2026 money: 450,000 × (131 / 100) = 589,500 A 2026 cost of 589,500 expressed in 2022 money: 589,500 × (100 / 131) = 450,000 ✓ Real change 2024 → 2026 in a cost that rose from 520,000 to 600,000: nominal change = +15.4% index change = 131 / 118 = +11.0% real change = (600,000 × 118/131) / 520,000 − 1 = 540,458 / 520,000 − 1 = +3.9%
Exam trap. Percentage changes are not additive and not symmetric. A 20% fall followed by a 20% rise leaves you at 96% of where you started, and a 50% overrun requires a 33% reduction to reverse. Any question involving a sequence of percentage movements is testing whether you multiply the factors rather than adding the percentages.

M4 Unit consistency and conversion

Cross-cutting no single primary element Supports 4.5.7 Finance · 4.5.10 Plan and control

The discipline that prevents most of the wrong answers in a timed calculation paper.

Effort units person-hours ↔ person-days ↔ person-months use the organisation's stated conversion, not 8 and 20 Time units working days ≠ calendar days working days ≠ elapsed days when availability < 100% Rate units per hour ↔ per day ↔ per month — check the divisor Money units thousands vs units; currency; nominal vs real (C12) Rate periods annual r to monthly: (1 + r)1/12 − 1, not r / 12 Method carry units through the calculation and check they cancel; estimate the order of magnitude before computing

Worked example

Conversions in this document 1 person-day = 8 hours (stated, not assumed) 1 person-month = 15.2 project-available days (from F3, not 21.7) 1 year = 260 working days = 215 productive = 182.75 project-available Effort chain 2,080 hours of function-point effort (H3) → 2,080 / 8 = 260 person-days → 260 / 15.2 = 17.1 person-months Using the nominal 21.7 days per month instead gives 12.0 person-months — a 30% understatement, and the error is invisible in the answer. Duration chain 260 person-days of effort, team of 3 Effort / headcount = 86.7 working days ÷ availability 0.70 = 123.8 working days ÷ 5 working days per week = 24.8 weeks × 7/5 for calendar = 34.7 calendar weeks ≈ 8 months The naive answer — 260/3 = 87 days ≈ 3 months — is out by 167%. Rate period annual discount rate 10%, monthly cash flows Wrong: 10% / 12 = 0.833% per month Right: 1.10^(1/12) − 1 = 0.797% per month Check: 1.00797¹² = 1.100 ✓ (1.00833¹² = 1.1047, a 0.47pt error) Money units a bid sheet showing "812" against a budget of "798,000" Almost certainly thousands. Confirm before comparing, and state the unit in every table header — the assumption that both are in the same unit is where six-figure errors originate. Order-of-magnitude check before computing 340 / 41.7: 340 is roughly 8× 42, so expect about 8. Getting 81.5 or 0.12 means a decimal or an inversion, caught in two seconds.
Exam trap. Annual rate divided by twelve is wrong for anything compounding, and it is the single most frequent finance error under time pressure. Second: person-months are not interchangeable between organisations, because the productive-days assumption differs — always state yours. Third: an answer with no unit attached earns no marks even when the arithmetic is right.

N  Change and transformation ICB4 4.5.13

N1 Change readiness and adoption measurement

Primary 4.5.13 Change and transformation · KCI 4.5.13.1 Assess the adaptability to change of the organisation(s) Also 4.3.1 Strategy

Whether the receiving organisation is ready for the change, how far adoption has actually gone, and what proportion of the promised benefit that adoption is delivering.

Readiness is scored before deployment across weighted dimensions, on the same scale, so that the weakest dimension can be identified — it is the one that predicts where adoption will stall. After deployment, headcount adoption is measured against eligible population, and then discounted by proficiency, because a user who has logged in once is not a user delivering the benefit the business case assumed. The benefit run-rate follows proficiency-adjusted adoption, not licences issued.

Readiness index R = Σ (wi × si) s on 1–5, Σwi = 1 Adoption rate A = active users / eligible users Proficiency P = observed throughput per user / target throughput Adjusted adoption A′ = A × P Benefit run-rate planned annual benefit × A′ Constraint the lowest-scoring readiness dimension caps adoption far more reliably than the mean does
100% 50% 0% business case assumption: full adoption by month 3 adoption 85% proficiency-adjusted 72% month 3: 65% adopted, 39% adjusted shaded area = benefit assumed but not realised 12 34 56 78 months after go-live
The gap that matters is not between plan and adoption, but between plan and proficiency-adjusted adoption. Benefits accrue at the lower line.

Worked example

Eligible population 480 users. Planned annual benefit 240,000. Readiness, assessed two weeks before go-live Dimension Weight Score Weighted Sponsorship visibility 0.25 4 1.00 Awareness of the change 0.20 4 0.80 Training coverage and capability 0.25 2 0.50 Capacity to absorb (other change) 0.15 2 0.30 Reinforcement and incentives 0.15 3 0.45 ---- ------ 1.00 3.05 Readiness index 3.05 / 5 = 61% Weakest dimensions: training (2) and capacity (2) — adoption will stall on capability, not on willingness. Adoption at month 3 Active users 312 / 480 = 65.0% Proficiency observed 18 transactions/user/week against a target of 30 = 60.0% Adjusted adoption 0.650 × 0.600 = 39.0% Benefit run-rate 240,000 × 0.390 = 93,600 per year Against a business case written on 240,000, the shortfall is 146,400 per year — and none of it appears in cost or schedule performance, because the project delivered what it promised.
Exam trap. Licences issued, accounts created and attendance at training are not adoption, and adoption is not benefit. The business case pays out on proficiency-adjusted adoption, so a project reporting 65% adoption against a plan of 100% is understating the shortfall by roughly half. Second: readiness measured once, at launch, tells you nothing about where adoption will stall — the value is in the weakest dimension, which is why a mean readiness score reported without its components is not usable. Third: a project can close on time and on budget with every deliverable accepted, and still realise 39% of its benefit. Cost and schedule performance say nothing about whether the change landed.

O  Index by ICB4 element

Perspective

4.3.1 Strategy

Primary C2C3C4C5C8I1I2I3K4 Supporting C1C6C7D6N1

4.3.4 Power and interest

Supporting J2J3

Practice

4.5.1 Project design

Primary K1K2K3 Supporting K4

4.5.2 Requirements and objectives

Primary H2 Supporting I1I2K2

4.5.3 Scope

Primary H1H4 Supporting B6H2H3L1

4.5.4 Time

Primary A1A2A3A4A5A6F5H3 Supporting B1B4D5F1F2F4L1L2L3L4L5

4.5.5 Organisation and information

Primary J1J4

4.5.6 Quality

Primary E1E2E3E4E5E6E7 Supporting M1M2

4.5.7 Finance

Primary C1C6C7C9C10C11C12C13 Supporting A4B1B2B6C2C3C4C5C8D2D4D5E1G2G4M3M4

4.5.8 Resources

Primary F1F2F3F4F6 Supporting F5G1L2

4.5.9 Procurement

Primary G1G2G3G4

4.5.10 Plan and control

Primary B1B2B3B4B5B6 Supporting A5D7H4I3L3L4L5M3M4

4.5.11 Risk and opportunity

Primary D1D2D3D4D5D6D7D8 Supporting A3C11C12M1M2

4.5.12 Stakeholders

Primary J2J3 Supporting J1

4.5.13 Change and transformation

Primary N1

Cross-cutting

These methods have no ICB4 element as a primary home. They are listed above under each element they support.

L1L2L3L4L5M1M2M3M4

IPMA publishes no official quantitative-methods syllabus, and each certification body sets its own exam format and weighting. This document covers the calculation methods that fall inside ICB4 practice competence elements. Confirm scope and format with your own certification body before relying on any part of it as an exam specification. All figures in the worked examples are invented and internally consistent; none represents a real project or a published benchmark.

Competence element and Key Competence Indicator references are quoted from the IPMA Individual Competence Baseline for Project, Programme and Portfolio Management, Version 4.0 © 2015 International Project Management Association. Quoted for study and commentary; IPMA is not affiliated with this document and does not endorse it. All other content © 2026 Fannar Örn Maximus.